[0020] A construction method of fluorine-containing waste water anticorrosion trench, comprising the following steps:
[0021] (1) Construction is carried out at a temperature of 15°C. During construction, the slope of the ditch bottom is 4%, and the edge of the ditch is slightly lower than the ground (so that the ground and the ditch do not collect liquid). Grinding the bottom of the ditch with a grinder or hand-made steel wool is used as the base layer. When there are potholes in the base course, the potholes should be cleaned and filled with acid mud pouring concrete or resin mortar;
[0022] (2) Clean the base layer once with cleaning agent and dry it with compressed air;
[0023] (3) Then paint the epoxy resin primer at least twice to be cured, whichever is not sticky to the touch;
[0024] (4) Lining with three layers of glass cloth after curing;
[0025] (5) Then line two layers of polyester felt on the glass silk cloth;
[0026] (6) Paint the MFE-2 resin topcoat on ...
Embodiment 2
[0030] A construction method of fluorine-containing waste water anticorrosion trench, comprising the following steps:
[0031] (1) Construction is carried out at a temperature of 25°C. During construction, the slope of the ditch bottom is 3%, and the edge of the ditch is slightly lower than the ground (so that the ground and the ditch do not accumulate liquid). Grinding the bottom of the ditch with a grinder or hand-made steel wool is used as the base layer. When there are potholes in the base course, the potholes should be cleaned and filled with acid mud pouring concrete or resin mortar;
[0032] (2) Clean the base layer twice with cleaning agent and dry it with compressed air;
[0033] (3) Then paint the epoxy resin primer at least twice to be cured, whichever is not sticky to the touch;
[0034] (4) Lining with three layers of glass cloth after curing;
[0035] (5) Then line four layers of polyester felt on the glass silk cloth;
[0036] (6) Paint the MFE-2 resin topcoa...
Embodiment 3
[0040] A construction method of fluorine-containing waste water anticorrosion trench, comprising the following steps:
[0041] (1) Construction is carried out at a temperature of 30°C. During construction, the slope of the ditch bottom is 3%, and the edge of the ditch is slightly lower than the ground (so that the ground and the ditch do not collect liquid). Grinding the bottom of the ditch with a grinder or hand-made steel wool is used as the base layer. When there are potholes in the base course, the potholes should be cleaned and filled with acid mud pouring concrete or resin mortar;
[0042] (2) Clean the base layer 3 times with cleaning agent and dry it with compressed air;
[0043] (3) Then paint the epoxy resin primer at least twice to be cured, whichever is not sticky to the touch;
[0044] (4) lined with four layers of glass cloth after curing;
[0045] (5) Then line six layers of polyester felt on the glass silk cloth;
[0046] (6) Paint the MFE-2 resin topcoat on...
PUM