Non-blasting construction method for dismantling pier to land bridge

A construction method and non-blasting technology, which is applied in building maintenance, construction, building construction, etc., can solve the problems of small working surface, high risk factor of work, unfavorable construction safety and other problems of cutting bridge main body, so as to achieve compact and operable construction process The effect of good performance and simple equipment
CN102493367AActive Publication Date: 2012-06-13CHINA RAILWAY SIXTH GRP CO LTD +2

Patent Information

Authority / Receiving Office
CN ยท China
Patent Type
Applications(China)
Current Assignee / Owner
CHINA RAILWAY SIXTH GRP CO LTD
Publication Date
2012-06-13

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
Patent Text Reader

Abstract

The invention discloses a non-blasting construction method for dismantling a pier to land the bridge. The method comprises the following steps of: forming a notch from the top middle of the pier; filling the notch with sandbag temporary supports; dismantling the pier top structures on the two sides of the sandbag temporary supports so that a girder falls on the sandbag temporary supports; placing sandbag temporary supports on the top surfaces on the two sides of the upper end of the pier respectively; and releasing sand in the middle sandbag temporary supports so that the girder falls on the sandbag temporary supports on the two sides until the end part of the bridge falls on the ground. The construction method has good safety, effectively controls the falling speed and amplitude of the bridge, ensures the construction safety, and is economical. The equipment is relatively simple, the construction cost is relatively low, and the operability is high. The dismantled machinery does not need to be placed on the bridge floor, and a bracket below the bridge floor is not required either; and moreover, the working surface is large, the construction is flexible, the operability is high, the construction process is compact, the construction period is short, and the practicability is strong.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention belongs to the technical field of bridge dismantling and construction, and in particular relates to a construction method for dismantling bridge piers without blasting to land the bridge. Background technique

[0002] Cable-stayed bridge, also known as cable-stayed bridge, is a bridge in which the main girder is directly pulled on the bridge tower with multiple prestressed rigid cable-stayed rods. A structural system composed of beams and bodies. The cable-stayed bridge mainly includes two piers, tower piers, bridge towers, main girder and multiple cable-stayed rods; the two bridge piers and the tower piers are vertically arranged at the two ends and the middle of the cable-stayed bridge respectively; the main girder spans the two On the top surface of a bridge pier and a tower pier, it is composed of a plurality of main girder sections connected end to end; the bridge tower is vertically installed on the main girder located on the upper...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More