Two-unit and six-step construction method for shallow-buried large-span tunnel
A construction method and tunnel technology, which is applied in tunnels, tunnel linings, earthwork drilling and mining, etc., to achieve the effects of strong promotion, construction safety, and large operating space
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0041] Example: The Meilin Tunnel of the Xiamen-Shenzhen Railway is a control project along the entire line. The mileage DK499+100~DK499+170 section passes through the Shuijing Reservoir. The buried depth of this section is 11m. The geological conditions from top to bottom are: silty clay, fully weathered granite , strongly weathered granite, the arch is made of silty clay, and the bottom of the tunnel is made of strongly weathered granite, which is one of the safety risk points in the construction of Meilin Tunnel. Before the excavation of the tunnel, a large pipe shed was used to split and grout to form a fan-shaped protective water blocking circle to prevent the seepage of the reservoir water and endanger the safety of the tunnel structure; according to the characteristics of geological conditions, the two-unit excavation method was adopted, that is, the excavation surface was divided into two Two units, the upper unit I and the lower unit II, use the middle partition 3 and ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com