Gob-side entry retaining gob-side filling supporting method
A first-level, guided support technology, which is applied in the direction of filling, earth square drilling, ground mining, etc., can solve the problems of large compression, the inability of the piled wall to support the roof in time and the low density of the piled wall
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0026] The filling process equipment includes: mixer, pumping system, 7 racks and 1 set of filling hydraulic support, flexible mold or canvas.
[0027] (1) Arrange and install filling equipment
[0028] Arrange the mixing station within 50m-100m from the working surface and connect the pumping system.
[0029] Install 7 sets of filling hydraulic supports, formwork support B in sequence behind the supports of fully mechanized mining face 2 With template bracket B 3 Between, template bracket C 2 And template support C 3 The width between the two is adjusted according to the width of the filling wall. All the lifting beams of the guide support A are in the closed state, that is, the complete set of hydraulic supports is in the state of minimum control distance (such as image 3 ).
[0030] Finally, hang the flexible mold or canvas on the template bracket B 2 With template bracket B 3 Between, template bracket C 2 And template support C 3 In between, a relatively closed filling space is co...