A method of filling and supporting beside gob-side entry retaining
A first-level, guided support technology, applied in the direction of filling, earth square drilling, shaft equipment, etc., can solve the problems of protection of unfavorable ecological environment, uncoordinated relationship between filling and mining, and large consumption of logs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0026] Filling process equipment includes: mixer, pumping system, 7 sets of 1 set of filling hydraulic support, soft mold or canvas.
[0027] (1) Layout and installation of filling equipment
[0028] Arrange the mixing station within 50m~100m from the working face and connect the pumping system.
[0029] Install 7 sets of filling hydraulic supports in sequence behind the support of the fully mechanized mining face, formwork support B 2 with formwork bracket B 3 Between, formwork bracket C 2 and template holder C 3 The width between them is adjusted according to the width of the filling wall, and all the cantilever beams of the guide bracket A are in the closed state, that is, the complete set of hydraulic supports is in the state of the minimum control of the top distance (such as image 3 ).
[0030] Finally, hang the soft mold or canvas on the formwork bracket B 2 with formwork bracket B 3 Between, formwork bracket C 2 and template holder C 3 Between them, a relativ...