Earthwork amount calculation method based on improved constraint irregular triangulation network construction method
A calculation method, triangulation technology, applied in constraint-based CAD, design optimization/simulation, special data processing applications, etc., can solve problems such as different calculation methods
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2021-04-30
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the field of calculating method of earthwork amount for site leveling in civil engineering construction, and in particular relates to an earthwork amount based on an improved constrained irregular triangular network construction method suitable for terrain conditions in eastern Zhejiang mountainous areas with large height difference fluctuations Calculation method. Background technique
[0002] The site leveling project refers to the transformation of the original landform of the project site according to the construction needs. Among them, the use of topographic survey results to accurately calculate the amount of earthwork, and then balance the amount of earthwork filling and excavation, and rationally select construction manpower and machinery equipment, is a reliable basis for controlling the construction plan and progress of the site, and is the key to affecting the cost and investment of the project. It is actually relate...
Examples
Embodiment Construction
[0024] The following descriptions are only preferred embodiments of the present invention, and do not limit the protection scope of the present invention. The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0025] Examples, see Figure 1 to Figure 4 Shown: A calculation method of earthwork quantity based on the construction method of improved constrained irregular triangulation, the specific steps are as follows:
[0026] Position the triangular elements at the start and end points of the constraint boundary line:
[0027] To realize that the project area is inserted into the unconstrained triangular network as a constraint boundary, at first the triangle unit where the boundary line endpoint is located needs to be positioned, and the present invention defines the following algorithm to realize this function;
[0028] Define the endpoint coordinates of the boundary line as Pn(X,Y), n is the endpoint number; de...