Soft stratum vertical shaft derrick structure and construction method thereof
A technology for weak strata and construction methods, which is applied in shaft equipment, earthwork drilling, wellbore lining, etc., and can solve problems such as low bearing capacity, poor self-bearing capacity, safety accidents, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] Such as figure 1 , figure 2 As shown, the present embodiment includes a shaft derrick structure for a weak formation, specifically comprising an outer well wall 1 arranged on the inner wall of the well, an inner well wall 2 is fixedly arranged on the inner wall of the outer well wall 1, and the A plurality of derrick foundations 3 are evenly arranged on the outer side of the outer well wall 1, and the derrick foundation 3 and the outer well wall 1 are arranged at intervals, and the outer well wall 1 and the derrick foundation 3 are arranged at intervals. There is an anti-fall beam structure 4, and the anti-fall beam structure 4 is fixedly connected with the derrick foundation 3 and the outer well wall 1 respectively, and a steel wire rope 5 is fixedly arranged on the outer well wall 1, and the steel wire rope 5 They are respectively fixedly connected with the outer well wall 1 and the derrick foundation 3 . By setting the derrick foundation 3 and connecting the derri...
Embodiment 2
[0045] This embodiment discloses a construction method for a shaft derrick structure in a weak stratum, including the following steps:
[0046] Step 1, measuring and setting out, according to the coordinate points and elevation points, use the total station to make a good point near the well, measure and set out on the surface according to the construction drawing, mark it with lime powder, and start the next step after the self-inspection is correct. one step construction;
[0047] Step 2: Excavation and leveling of the foundation pit, using an excavator to excavate, excavating the inside of the wellbore to the depth of the upper opening of the anti-fall beam structure 4 at one time, and then using a loader to compact the foundation pit and leveling manually;
[0048] Step 3, construction of the derrick foundation 3 and the anti-fall beam structure 4, pouring a plurality of derrick foundation 3 and the anti-fall beam structure 4 around the foundation pit;
[0049] Step 4, co...
PUM

Abstract
Description
Claims
Application Information

- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com