[0019] Such as figure 1 , 2, the process flow of the construction method of the present invention is: before the fixed pile pipe 4, the sea construction preparation work and the factory prefabrication of the fixture are carried out simultaneously, on the one hand, carry out sea underwater survey, positioning and sonar buoy calibration, on the other hand On the one hand, the fixing device 6 is pulled and transported to the beach site to be assembled with the fixed pile pipe 4, and then the whole is shipped and transported in place. Pile driver 2, fixture 6, fixed pile pipe 4 etc. are hoisted together by floating crane 11 on the construction ship 9, and fixed pile pipe 4 is entered into the center of righting frame 3. Utilize the sonar device 3.11 on the centralizing frame 3 to find the suspended pipe section, and guide the centralizing frame 3 to be precisely in place. Then with pile driver 2 fixed pile pipe 4 is driven into the seabed, and fixture 6 is put in place; Meanwhile...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com