Method for building subway station by expansively digging large-diameter shield tunnel
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- BEIJING RAIL TRANSIT CONSTR MANAGEMENT
- Publication Date
- 2012-03-28
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
Technical field
[0001] The invention relates to a method for expanding a large-diameter shield tunnel to construct a subway station, and belongs to the technical field of underground construction engineering. Background technique
[0002] At present, the construction methods of Beijing subway mainly include open-cut method, shallow-buried and concealed method, and shield method. The construction of subway sections generally adopts the shield method; the stations generally adopt the open excavation method or the shallow buried excavation method. Interval shield construction is often restricted by station construction, which makes the advantages of shield construction not fully utilized, resulting in the extension of the construction period and the increase of construction costs of subway lines.
[0003] With the densification of Beijing's rail transit network, subway construction is facing an increasingly complex environment: narrow roads, heavy ground traffic, a large number of ne...