Parallel construction method for shield arrival tunnel portal ring beam and shield crossing station

A receiving hole and shield technology, which is applied in earthwork drilling, shaft lining, tunnel lining, etc., can solve the problems of high cost, uncontrollable quality, long construction period, etc., achieve advanced technology, eliminate the influence of shield tunneling, and process simple effect

Active Publication Date: 2013-04-10
2ND ENG CO LTD OF CHINA RAILWAY 12TH BUREAU GRP +1
View PDF4 Cites 22 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] In order to solve the problems of long construction period, high cost and uncontrollable quality in the construction of the door ring beam after the completion of the existing station shield tunnel, the present invention provides a parallel construction method for the shield receiving door ring beam and the shield passing through the station

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Parallel construction method for shield arrival tunnel portal ring beam and shield crossing station
  • Parallel construction method for shield arrival tunnel portal ring beam and shield crossing station
  • Parallel construction method for shield arrival tunnel portal ring beam and shield crossing station

Examples

Experimental program
Comparison scheme
Effect test

example

[0037] Changsha Metro Changsha Metro Line 2, 7 standard construction three shield sections, the shield needs to pass the station twice, in Yingbin Road Station and Furong Square Station, use polyurethane to carry out secondary supplementary grouting on the shield receiving segment , cancel zero-ring segment assembly. It is used to install I-beam and welded steel plate support rails on the steel ring of the portal to realize the synchronous operation of the construction of the portal ring beam and the shield tunneling. The pump pipes are pre-embedded in the middle plate and the roof, so that the station does not need to leave temporary hoisting openings, and the traffic can be resumed one year in advance. Now it has been extended to the construction of the receiving portals in the three shield sections of the 10th standard of Line 1, which has greatly improved the station and shield construction efficiency, proving that the technology is advanced, practical, flexible in constru...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to the field of tunnel shield construction, in particular to a parallel construction method for a shield arrival tunnel portal ring beam and a shield crossing station. According to the parallel construction method for the shield arrival tunnel portal ring beam and the shield crossing station, the problems of long construction period and high cost because tunnel portal ring beam construction is carried out after the shield tunnel of the traditional station is finished are solved. The parallel construction method for the shield arrival tunnel portal ring beam and the shield crossing station comprises the following steps of: reserving a pump pipe on a middle plate and a top plate of the station; during shield arrival, carrying out secondary after-grouting to the back of a pipe piece by polyurethane; cancelling zero ring pipe piece splicing; after a shield tail leaves the tunnel portal ring beam, overlaying I steel on tunnel portal ring steel; welding a steel plate on the I steel; erecting a groined type rack platform on the tunnel portal steel ring; binding the tunnel portal ring beam reinforcing steel bar; installing an annular template and an end tip template; and directly pouring tunnel portal ring beam concrete by a station embedded pump pipe. Tunnel portal ring beam and shield tunneling can be synchronously carried out, and the influence on the shield tunneling by the tunnel portal ring beam construction is avoided. The parallel construction method for the shield arrival tunnel portal ring beam and the shield crossing station has the advantages of simple technology, advanced technology, flexible working procedure regulation, no construction interference and favorable economic benefit and social benefit.

Description

technical field [0001] The invention relates to the technical field of tunnel shield construction, in particular to a parallel construction method of a ring beam of a shield receiving portal and a shield passing station. Background technique [0002] With education and household registration management causing more and more urban residents, and the traffic congestion caused by people traveling by car, most developed second-tier cities are now starting to build subways. However, due to the particularity of shield tunneling construction, it is necessary to install a portal ring beam at the end of the shield tunnel at the station, which requires a temporary hoisting opening to be reserved for the station construction to remove the shield receiving zero ring. After the station, a track was laid at the bottom of the steel ring of the portal for battery vehicles to transport construction materials such as segments, synchronous grouting slurry, grease, etc., and to transport shiel...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/14E21D11/00E21D11/10E21D9/06
Inventor 王宗勇毋海军雷军赵香萍常鑫王剑田晓峰
Owner 2ND ENG CO LTD OF CHINA RAILWAY 12TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products