The invention provides a construction method for a permanent and temporary combined formwork-erecting-free box
culvert to penetrate through an existing extra-large bridge in a limited space. The method comprises the following steps: S1, leveling
a site and drilling; s2, construction of cast-in-place piles; s3, high-pressure jet grouting
pile construction; s4, constructing a concrete top beam and a
continuous beam; s5, excavation of the foundation pit; s6, hanging a net and spraying concrete; s7, reinforcing steel bars are bound on the box
culvert, and an inner formwork is reinforced; and S8, box
culvert concrete pouring. According to the construction method, construction of penetrating through the extra-large piers in the limited space is achieved, safety and stability of a foundation pit slope are effectively maintained, earthwork collapse is prevented, the supporting piles replace formworks and wall concrete of
pier walls in a permanent and temporary combination mode, the formwork manufacturing and installing
engineering amount and the dismantling amount of temporary supporting
pile engineering are effectively reduced, and the construction efficiency is improved. The construction period is shortened, the cost is saved, and the box culvert super-bridge penetrating construction is efficiently and safely completed.