A reverse construction method
A construction method and reverse work technology, which is applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve the problems of poor construction environment, slow excavation speed, and reduced construction efficiency, so as to improve time and space efficiency, improve construction speed, and save energy. The effect of building materials
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] according to Figure 1 to Figure 8 As shown, the reverse construction method is used to construct the three underground floors. The foundation pit is long and strip-shaped. After calculation, under the condition of ensuring the necessary working plane at the bottom of the pelvic cavity 3, the pelvic cavity 3 can be directly dug to the third underground floor. The specific construction steps are as follows:
[0039] A. Design the foundation pit: according to figure 2 As shown, the shape and size of the three-story underground foundation pit are designed, and an enclosure structure 1 is set up around the foundation pit. The enclosure structure 1 adopts an underground diaphragm wall, and steel columns 2 are set up at the same time;
[0040] B. Open and cut earthwork: according to image 3 As shown, the pot cavity 3 is excavated from the top of the soil layer, and a section of flat soil 31 is left between the opening of the top of the earth and the enclosure structure; ...
Embodiment 2
[0046] Different from the above-mentioned embodiment 1, according to Figure 1 to Figure 9 As shown, the reverse construction method is used to construct 4 underground floors. The foundation pit is long and strip-shaped. After calculation, in order to ensure the necessary working plane at the bottom of the pelvic cavity 3, the maximum depth of the pelvic cavity 3 can be dug to the 3rd underground floor. The specific construction Proceed as follows:
[0047] A. Design the foundation pit: design the shape and size of the three-story foundation pit underground, and set up an enclosure structure 1 around the foundation pit. The enclosure structure 1 adopts an underground diaphragm wall and sets up steel columns 2 at the same time;
[0048] B, earthwork open excavation: excavate the pot cavity 3 from the top of the soil layer, and leave a section of smooth soil 31 between the opening on the top of the earthwork and the enclosure structure; °, the excavation depth is three floors u...
Embodiment 3
[0054] The difference from the above-mentioned Example 1 is that the width of the construction pit is doubled, and step B adopts the method of excavating a pelvic cavity 3 alone, which is not enough to make the bottom of the pelvic cavity 3 exceed the design depth of the underground layer. According to Figure 10 As shown, in step B, two side-by-side pelvic cavities 3 are cut out, and the rest of the steps are the same as those in embodiment 1.
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


