A rapid subsidence construction device for a pile-anchor press-in caisson

A construction device and press-in technology, which is applied to caissons, sheet pile walls, foundation structure engineering, etc., can solve problems such as unfavorable shaft wall stress, high construction site requirements, and occupation of construction sites, and achieve simple and continuous construction procedures. The construction area is small and the effect of speeding up the construction speed

CN108487281BActive Publication Date: 2020-07-03SHANGHAI URBAN CONSTRUCTION MUNICIPAL ENGINEERING (GROUP) CO LTD
6 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Publication Date
2020-07-03

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a rapid sinking construction device for a pile anchor press-in type sinking well. The well wall of the sinking well is provided with a plurality of vertical through holes in the peripheral direction in a spaced manner. The rapid sinking construction device is characterized by comprising anchor piles, anchor cables and cross-core jacks; the anchor piles are pre-buried in soil directly below the designed elevation of the sinking well to form counter-force ground anchors, the cross-core jacks are arranged above the through holes of the well wall of the sinking well, the anchor cables penetrate through the through holes, the lower end of the anchor cables are connected to the anchor piles, the upper ends of the anchor cables penetrate through the cross-core jacks and are fixed by anchoring nuts. The rapid sinking construction device has the advantages that the anchor piles, the anchor cables and the cross-core jacks form the construction device which provides sinking force for the sinking well, site limitation is avoided, the rapid sinking construction device is suitable for sinking wells of various shapes, the sinking posture of the sinking well can be effectively controlled, additional external force cannot be generated for the sinking well wall, the stress of the sinking well in the sinking process can be uniform and steady, and unsafe situations that thesinking is inclined, sunk suddenly and the like are effectively avoided.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the technical field of caisson construction, in particular to a rapid sinking construction device for a pile-anchor press-in type caisson. Background technique

[0002] The caisson is a construction method for underground engineering and deep-buried foundations. With the development of modern construction technology and construction machinery, the caisson has gradually become a common type of enclosure structure for deep-buried underground structures, and it is economical and reasonable. , Simple structure, easy to guarantee engineering quality and other advantages, it is widely used in underground structures, foundations, foundation pit support and other projects.

[0003] The sinking of the caisson mainly relies on its own weight to overcome the frictional resistance between the well wall and the soil and the resistance under the blade foot to sink to the design elevation. The choice of caisson sinking construction method de...

Examples

Embodiment

[0027] Example: such as Figure 1-8 As shown, this embodiment specifically relates to a rapid sinking construction device for pile-anchor press-in caissons, including anchor piles 2, anchor cables 3 and through-hole jacks 5, and the anchor piles 2 are pre-buried below the design elevation of the caisson 1 The soil forms a counter-force ground anchor, and the through-hole jack 5 is arranged above the well wall of the caisson 1, and the anchor cable 3 runs through the well wall of the caisson through the through hole 4, and one end is connected to the anchor pile 2, and the other end is connected to the oil cylinder of the through-hole jack 5 upper end. The construction device is used to provide a stable sinking force for the caisson 1, and can control the descending posture of the caisson 1, and has simple construction procedures, and is suitable for various irregularly shaped caissons.