A maintenance method for a high-speed rail on-board isolation transformer
A technology for isolating transformers and transformers, applied in the field of transformers, can solve the problems of transformer installation, complicated operation process, uneven heat dissipation, etc., and achieve the effect of increasing service life and uniform heat dissipation
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2019-10-08
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of transformers, in particular to a maintenance method for a high-speed railway vehicle-mounted isolation transformer. Background technique
[0002] Isolation transformer refers to a transformer with electrical isolation between the input winding and the output winding. The isolation transformer is used to avoid accidental contact with the live body at the same time. The isolation of the transformer is to isolate the respective currents of the primary and secondary coils. In the early days, it was used in the electric power industry in European countries, and was widely used in the control power supply of general circuits in the electronics industry or industrial and mining enterprises, machine tools and mechanical equipment, as well as the power supply of safety lighting and indicator lights.
[0003] However, the traditional high-speed rail on-board isolation transformers are transported by cranes and trucks. Howeve...
Examples
Embodiment Construction
[0026] In order to make the technical means, creative features, goals and effects achieved by the present invention easy to understand, the present invention will be further described below in conjunction with specific embodiments.
[0027] Such as figure 1 , figure 2 and Figure 4 As shown, a kind of high-speed rail on-board isolation transformer maintenance method described in the present invention, the method comprises the following steps:
[0028] S1, a pipe is installed on the side of the high-speed rail carriage; one end of the pipe communicates with the outside of the carriage, the other end of the pipe communicates with the interior of the carriage, and the end of the pipe in the carriage is located next to the high-speed rail on-board isolation transformer. When the high-speed rail is running, the negative The heat on the transformer is sucked out to achieve heat dissipation;
[0029] S2, installing a dust-proof net at the end of the pipeline in S1 to prevent dust...