Construction method of river-crossing open-excavation deep foundation pit
A construction method and technology for deep foundation pits, which are applied in excavation, infrastructure engineering, construction, etc., can solve the problems of complicated underground pipelines, difficult construction methods, and heavy road traffic, and achieve fast construction speed, good effect, and support. stable effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0033] A kind of river-crossing open-cut deep foundation pit construction method of the present invention comprises the following steps:
[0034] A. Divide the construction area of the foundation pit to be constructed into two parts: the first-phase foundation pit and the second-phase foundation pit, of which the first-phase foundation pit is a river-crossing open-cut foundation pit, and the second-phase foundation pit is a non-river-crossing open-cut foundation pit , set up cofferdams to intercept the river upstream and downstream of the first-stage foundation pit, and set up a diversion channel to divert the river. The diversion channel partly passes through the second-stage foundation pit. After the diversion is completed, the existing For the river course, the broken muck shall be cleaned and backfilled with soil;
[0035] The cofferdam adopts a steel mold cofferdam, laying 20mm thick bamboo plywood on the water-facing surface and attaching an anti-seepage membrane cloth...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com