A kind of ballasted turnout inserting construction method
A construction method and turnout technology, applied to roads, tracks, laying tracks, etc., to achieve the effect of improving operation efficiency and construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0062] Combine below Figure 1-10 Describe in detail the preferred technical scheme of the ballasted turnout insertion construction method:
[0063] Such as figure 1 Shown, a kind of ballasted turnout insert laying construction method, comprises the following steps:
[0064] Step 1: Pre-paved location selection; during site selection of ballasted turnouts, an open space is reserved on one side of the line as a traversing turnout assembly site. The traversing turnout assembly site needs to meet the overall assembly requirements of the turnout; For the site that meets the overall assembly conditions of the turnout, according to the actual situation, select the idle track or dead end line near the area where the turnout is to be laid as the assembly site, or directly use the movable turnout assembly platform;
[0065] The movable turnout assembly platform preferably adopts the patent number ZL201910561849.9, the subject of which is a technical solution for a movable turnout ass...