A concrete and closed technology, applied in the direction of instruments, bridges, bridge parts, etc., can solve the problems of entering the warehouse, the vibrator cannot be vibrated effectively, and the concrete voids, etc., to improve the detection efficiency, improve the detection success rate, and ensure the perfusion. quality effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0073] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0074] like figure 1 and figure 2 As shown, the method for pouring concrete in the closed column may further comprise the steps:
[0075] Step 1, construction preparation, cleaning up the sundries on the construction joint surface 200;
[0076] Step 2, building pile formwork 7;
[0077] Step 3, connect the pipeline;
[0078] Step 4, pouring concrete:
[0079] Step 4.1, laying a concrete base on the construction joint surface 200 of the permanent underpinning beam 9, the upper end of the concrete base is lower than the height of the stop valve 2, and the thickness of the concrete base is 15 mm;
[0080] Step 4.2, pouring the concrete solid layer on the concrete base, the concrete solid layer pouring is carried out in layers, and the pouring thickness is not greater than 1.25 times the length of the action part of the attached vib...