Method for treating saline-alkali soil of coastal saline-alkali soil through combination of engineering and chemical improvement
A saline-alkali land and engineering technology, applied in the field of saline-alkali land treatment, can solve problems such as soil properties change, soil structure deterioration, and poor soil moisture status, and achieve the effect of assisting plant growth and improving the growth environment.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] A method for controlling saline-alkali land by combining engineering and chemical improvement on coastal saline-alkali land, the steps are as follows:
[0030] (1) Treatment before laying of hidden pipes
[0031] Remove weeds and rocks on the original landform to ensure that the land has a foundation for farmland planting; level the land to ensure that engineering equipment can enter the field for operations;
[0032] (2) Laying of hidden pipes
[0033] Before laying the hidden pipe, re-measure the elevation point to ensure that the value is correct, lay the line according to the preset hidden pipe, and insert the benchmark at the beginning and end. Carry out laser measurement according to the slope calculated according to the design to ensure the slope of the buried pipe, use an excavator to excavate the trench for the buried pipe, fill it according to the selected filter material of the hidden pipe, and then lay the hidden pipe. After the laying is completed, backfi...
Embodiment 2
[0050] A method for controlling saline-alkali land by combining engineering and chemical improvement on coastal saline-alkali land, the steps are as follows:
[0051] (1) Treatment before laying of hidden pipes
[0052]Remove weeds and rocks on the original landform to ensure that the land has a foundation for farmland planting; level the land to ensure that engineering equipment can enter the field for operations;
[0053] (2) Laying of hidden pipes
[0054] Before laying the hidden pipe, re-measure the elevation point to ensure that the value is correct, lay the line according to the preset hidden pipe, and insert the benchmark at the beginning and end. Carry out laser measurement according to the slope calculated according to the design to ensure the slope of the buried pipe, use an excavator to excavate the trench for the buried pipe, fill it according to the selected filter material of the hidden pipe, and then lay the hidden pipe. After the laying is completed, backfil...
Embodiment 3
[0066] A method for controlling saline-alkali land by combining engineering and chemical improvement on coastal saline-alkali land, the steps are as follows:
[0067] (1) Treatment before laying of hidden pipes
[0068] Remove weeds and rocks on the original landform to ensure that the land has a foundation for farmland planting; level the land to ensure that engineering equipment can enter the field for operations;
[0069] (2) Laying of hidden pipes
[0070] Before laying the hidden pipe, re-measure the elevation point to ensure that the value is correct, lay the line according to the preset hidden pipe, and insert the benchmark at the beginning and end. Carry out laser measurement according to the slope calculated according to the design to ensure the slope of the buried pipe, use an excavator to excavate the trench for the buried pipe, fill it according to the selected filter material of the hidden pipe, and then lay the hidden pipe. After the laying is completed, backfi...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com