Building engineering construction quality acceptance method based on BIM
What is Al technical title?
Al technical title is built by PatSnap Al team. It summarizes the technical point description of the patent document.
A technology of construction quality and construction engineering, applied in the field of project quality management, can solve problems such as inconsistent opinions, untimely filling of acceptance record forms, etc., to facilitate rectification work, improve project construction quality, and prevent loss
Pending Publication Date: 2021-08-31
JIANGSU SUZHONG CONSTR GROUP
View PDF0 Cites 2 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
It consists of three parts: the self-inspection and acceptance of the construction team, the self-inspection and acceptance of the completion of the project department, and the random inspection and acceptance of the company. However, the existing project quality acceptance requires multiple engineering acceptance personnel and construction personnel, and there are often disagreements in the acceptance process. , and there is a problem that the acceptance record form is not filled in time
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Examples
Experimental program
Comparison scheme
Effect test
Embodiment 1
[0071] A BIM-based construction engineering construction quality acceptance method includes the following steps:
[0072] S1, program review;
[0073] A. Construction units require construction organization design, construction plan, etc. according to drawings, contract documents;
[0074] B. The construction unit conducts internal approval and complete procedures, including internal approval including construction organization design and construction plan approval work;
[0075] C, the construction unit is reviewed for construction technical documents;
[0076] d, the supervision unit batch opinion, if not approved, the A, B, C items of the S1 step, if the regulatory unit approval, the supervision unit formation group, the plan report;
[0077] e, the construction unit is based on the approved opinion and technical documentation, in which the technical handling work includes, construction organization design, construction and sub-project construction technology;
[0104] A. Construction units require construction organization design, construction plan, etc. according to drawings, contract documents;
[0105] B. The construction unit conducts internal approval and complete procedures, including internal approval including construction organization design and construction plan approval work;
[0106] C, the construction unit is reviewed for construction technical documents;
[0107] d, the supervision unit batch opinion, if not approved, the A, B, C items of the S1 step, if the regulatory unit approval, the supervision unit formation group, the plan report;
[0108] e, the construction unit is based on the approved opinion and technical documentation, in which the technical handling work includes, construction organization design, construction and sub-project construction technology;
[...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
PUM
Login to View More
Abstract
The invention discloses a BIM-based building engineering construction quality acceptance method. The method comprises the following steps: S1, performing scheme reporting and auditing; a, the construction unit compiles construction organization design, construction schemes and the like according to the requirements of drawings, contract files and the like; b, the construction unit carries out internal examination and approval, procedures are complete, the internal examination and approval comprises construction organization design and construction scheme examination and approval work; c, the construction unit carries out construction technical file examination and approval work. The quality inspection and acceptance working method for engineering construction has fairness and authority, and is a correct acceptance structure obtained through a scientific model information comparison detection means; therefore, a building group carrying out quality acceptance work through the BIM-based building engineering construction quality acceptance method can truly, objectively and accurately reflect the engineering construction quality, and the original technology influencing the engineering quality can be detected and analyzed through the building structure model established through the BIM technology, so improvement measures are taken in a targeted manner.
Description
Technical field [0001] The present invention discloses a BIM-based construction quality acceptance method, which belongs to the technical field of engineering quality management. Background technique [0002] Engineeringquality management refers to system management activities that guarantee and improve engineering quality, using a complete set of quality management systems, means and methods. The quality of the project is good and bad, is a fundamental issue. Project construction, large investment, completion and use period, only quality standards can be put into production and delivery, play investment benefits, combined with professional technology, management and management, to meet social needs. There is a strict supervision and inspection method for many countries in many countries in the world. [0003] Engineering acceptance refers to the process of assessing the quality and results of engineering construction after the completion of the project. From the inspection and ...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.