Compulsory pouring device and construction method of bored pile underwater concrete
Patent Information
- Authority / Receiving Office
- CN Β· China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- DALIAN AERBIN GROUP
- Publication Date
- 2011-06-22
- Estimated Expiration
- Not applicable Β· inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
Technical field:
[0001] The invention relates to the field of building construction, in particular to forced pouring equipment and a construction method for underwater concrete of cast-in-place piles. technical background:
[0002] In the field of building construction, during the construction of cast-in-situ piles, if the soil quality of the cast-in-situ piles is poor and mud retaining walls are used, or the groundwater in the piles is rich, underwater concrete pouring technology is usually used. In order to prevent the concrete in the conduit from falling easily during the pouring process, high slump concrete (generally 140mm-190mm, different slump corresponding to gravel with different particle sizes) is usually used, but the diameter of the conduit, pile Influenced by many factors such as the specific gravity of the inner mud retaining wall and the embedment of the end of the conduit, the problem that the concrete in the conduit is not easy to fall still often occurs. ...