Construction method of long auger drilling concrete-grouted back-plugged profile steel piles
A technology of long auger drilling and pouring concrete, which is applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., which can solve the problems of low construction efficiency, large site occupation, and hole gaps, and achieve simple construction procedures and small construction site occupation , high work efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0026] See implementation legend Figure 1 to Figure 8 .
[0027] exist figure 1 The mid-length auger rig 1 is shifted and centered, and the center of the long auger rod is controlled to be centered with the center of the pile.
[0028] exist figure 2 The middle and long auger drilling rig 1 drills holes to the design elevation.
[0029] exist image 3 The middle-length auger rig 1 pumps concrete to the top of the pile while rotating the hole, and overfills a part of the concrete.
[0030] exist Figure 4 In the middle, connect the manufactured section steel pile 3 with the vibration connection device 2, connect the flange plate 2.1 of the vibration connection device 2 with the spring vibrating hammer 6, use a crane to lift it, and then center and sink the section steel pile.
[0031] exist Figure 5 The medium-sized steel pile is sunk to the design position, the T-shaped bayonet is removed, and the pile is formed.
[0032] exist Figure 6 Make the vibration connecti...