Formwork filling construction technology between gob-side entry retaining frame
A construction technique and a technology for retaining roadways, which can be applied to fillings, safety devices, mining equipment, etc., and can solve problems such as potential safety hazards and support delays in support, so as to improve safety, improve work efficiency, and save production materials Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0008] Such as figure 1 As shown in the diagram, a construction process of molding and filling between gob-side entry retaining frames, the steps are to leave a space at the position where support needs to be reserved in the support group of the excavation face, and the supports 1 and 3 on both sides of the space Install the support frame 2 on the top, and then carry out the molding 4 filling operation in the safe space formed between the support frame 2 and the two supports 1,3.
[0009] After the mold making is completed, the filling operation is carried out. After the filling is completed, the normal coal cutting operation starts. When the coal mining face is advanced enough for the mold making distance and the filling material is solidified, the demoulding begins for the next mold making operation. When the coal shearer cuts enough for 4 cycles and reaches enough mold making space, mold making and filling will be done in time; after filling, coal cutting will continue, and...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com