The invention discloses a
karst-related area interval underpass construction method, and relates to the technical field of
tunnel engineering, and the
karst-related area interval underpass construction method comprises the following steps: carrying out field classification and improvement treatment on soft rock
muck discharged by
shield tunneling to obtain aggregate
muck which can be directly used for backfilling and fine-grain
muck which can be used for preparing grouting
slurry; muck improvement
slurry is prepared from fine muck,
karst cavities on the construction path are pre-filled, and advanced grouting reinforcement is conducted on the stratum of the underpass section; during the period that
shield tunneling penetrates through a karst area or penetrates through an existing structure under the karst area, synchronous grouting is conducted through muck improvement
grout, and grouting parameters and tunneling parameters are dynamically adjusted according to real-time
monitoring data; and after segmental lining is completed, compensation grouting is conducted through muck improved
grout, and a stacked grouting
supporting system is formed in the surrounding rock. According to the method, the shield muck can be recycled, the grouting material cost is reduced, and the safety and reliability of shield underneath pass construction are ensured.