Construction method of opening locked steel tube pilecofferdam

A construction method and technology of steel pipe piles, applied in infrastructure engineering, architecture, bridge construction, etc., can solve the problem that the bending modulus of steel sheet pile cofferdam cannot meet the required section resistance moment, and it is difficult for large tugboats and floating cranes to enter , Intensive construction can not be carried out and other problems, to achieve the effect of high rigidity, strong sealing, simple and convenient support

Active Publication Date: 2009-12-30
CHINA RAILWAY 18TH BUREAU GRP CO LTD
View PDF5 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Therefore, if ordinary steel sheet pile cofferdams are used, the denseness of the internal support makes the construction impossible. Moreover, due to the deep insertion depth and pumping depth, the internal and external water side pressure is relatively large, and the flexural modulus of the steel sheet pile cofferdam It is far from meeting the required cross-sectional resistance moment; if steel box cofferdams are used, a large amount of steel, large construction sites, large transportation, lifting equipment and assembly platforms are required
Due to the limitation of navigation conditions and floating crane equipment, it is difficult for large tugboats and floating crane equipment to enter the pier construction site, so it is also difficult to use steel box cofferdams

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of opening locked steel tube pilecofferdam
  • Construction method of opening locked steel tube pilecofferdam
  • Construction method of opening locked steel tube pilecofferdam

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0022] A method for constructing a cofferdam of interlocking steel pipe piles, which is carried out according to the following steps: ①Processing steel pipe columns: such as figure 1 As shown: the female buckle 2 and the male buckle 3 are respectively processed on the spiral tube 1; the male and female buckles are made of unequal angle steel, which not only saves materials, but also solves the problem of small locking space. In order to ensure the accuracy of positioning during the insertion and driving of steel pipe piles and the space position of the inner cavity of the box, we added a stopper 4 in the design. The above-mentioned male buckle and the female buckle are made of unequal angle steel and the axes of the male buckle and the female buckle are 180°, and the corner pipe 5 is 90°. ② if figure 2 As shown: the steel pipe columns are connected to each other from the beginning along the surrounding of the cap to form a whole steel pipe column, and each one is lifted into...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

A construction method of the locking steel pipe pile cofferdam can be carried out according to the following procedures: first is the processing of the steel pipe pile: a female thread and a male thread are fabricated on the spiral pipe; second is that steel pipe piles are connected mutually into an integrated steel pipe pile along the surrounding of the pile cap from beginning to end, all of which are lifted to the place and settled to the designed location by machine; third is grouting of the locking: the locking place of the female thread and the male thread is lined with a clothe bag and the slurry is poured into the bag; fourth is that a support in a cofferdam is arranged; final is that the concrete pouring of a sealing bottom is carried out. The invention has the advantages and the positive effects as follows: 1. flexible connection and being suitable for the assembly of various cofferdams; 2. large section strength and stiffness, and simple and convenient support; 3. simple processing and no need of the large-scale machinery and equipment, no requirement of large-scale floating facilities, and synchronized installation with the pile foundation work; 4. convenient operation and no limitation of the deepwater and the sludge; 5. sufficient rigidness which meet the settlement stiffness and strength with machinery; 6. strong leak tightness.

Description

Technical field: [0001] The invention relates to a construction technology of a bridge pier cofferdam, in particular to a construction method of a locking steel pipe pile cofferdam. Background technique: [0002] For bridge piers with large and rectangular caps, they cannot form a stable force-bearing structure to resist external forces like circular cofferdams. Therefore, if ordinary steel sheet pile cofferdams are used, the denseness of the internal support makes the construction impossible. Moreover, due to the deep insertion depth and pumping depth, the internal and external water side pressure is relatively large, and the flexural modulus of the steel sheet pile cofferdam It is far from meeting the required cross-sectional resistance moment; if a steel box cofferdam is used, a large amount of steel, a large construction site, large transportation, lifting equipment and an assembly platform are required. Due to the limitation of navigation conditions and floating crane ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E02D19/04E01D19/02E01D21/00
Inventor 张运书辛自洋
Owner CHINA RAILWAY 18TH BUREAU GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products