Prefabricated plasterboard installation structures
A technology for installing structures and gypsum boards, applied in building components, building structures, buildings, etc., can solve problems such as cracking of gypsum board ceilings, high repair costs, and bending of Yin and Yang corners, saving money and labor in construction, and optimizing the layout. , the effect of reducing the load
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2016-04-13
Smart Images
Figure 1 Figure 2
Abstract
Description
technical field
[0001] The present invention relates to a prefabricated gypsum board installation structure. Background technique
[0002] At present, most of the decoration industry in my country has quality problems such as cracking of gypsum board ceilings, bending of yin and yang angles in stacked shapes of gypsum board ceilings, and unevenness of light troughs and standing boards caused by differences in indoor temperature, humidity and subtle changes in building structures. Large and often difficult to completely repair. This has plagued the construction of gypsum board ceilings in decoration for a long time, and there has been no good solution. In this regard, how to adopt new technologies, new processes, and new materials to ensure that the gypsum board ceiling does not appear cracking or bending of internal and external corners, so as to make the gypsum board ceiling more visually appealing, requires special research. Contents of the invention
[0003] The purpos...
Examples
Embodiment 1
[0015] Embodiment one: if figure 1 As shown, a prefabricated gypsum board installation structure includes a prefabricated gypsum board 2 and a keel system. The keel system includes a side keel 1 fixed to the wall and a side keel 1 fixed to the top of the building. The prefabricated gypsum board 2 is In cascade modeling, one side of the prefabricated gypsum board 2 is connected to the side keel 1 fixed to the wall, and the other side of the prefabricated gypsum board 2 is connected to the side keel 1 fixed to the top surface of the building.
Embodiment 2
[0016] Embodiment two: if figure 2 As shown, a prefabricated gypsum board installation structure includes a prefabricated gypsum board 2 and a keel system. The keel system includes a screw 6, a main keel 4, and an auxiliary keel 3. The upper end of the screw 6 is fixed to the top surface of the building. 6. A main keel 4 is arranged at the lower end, and the main keel 4 is connected with the auxiliary keel 3. The prefabricated gypsum board 2 is Z-shaped, and the gypsum board surfaces of different heights of the prefabricated gypsum board 2 are respectively connected with the auxiliary keel 3 of different heights.