Scheduling method based on bottleneck procedure
A bottleneck process and product technology, applied in data processing applications, forecasting, instruments, etc., can solve the problem of manual production scheduling not being able to optimize production scheduling.
Image
Examples
Embodiment 1
[0048] Use the linear programming algorithm to establish a mathematical model for the long-term planning stage, figure 2 Shows the mathematical model established for the long-term planning phase using the linear programming algorithm according to an embodiment of the present invention, such as figure 2 As shown, the first part is the output of the bottleneck process, in figure 2 Including four production lines are A01, A05, A07, A08, production line A01 assembles two types of parts A and C, production line A05 assembles four types of parts B, W, C, T, production line A07 assembles A , B, W, C, D five types of parts, production line A08 assembles A, T two types of parts, the following four types of A, B, C, D parts are used as examples to illustrate, other types of parts the same way.
[0049] figure 2 The second part is the demand quantity of the product order, which is the quantity of each type of parts in the product order that needs to be assembled within a preset ti...
Embodiment 2
[0068] Since the orders of one month or one week will not change greatly, it can be used as the basis for accurate and all-process production scheduling, and the linear programming algorithm is used to establish a mathematical model for the short-term production scheduling stage. image 3 It shows the establishment of a mathematical model of the short-term production scheduling stage using a linear programming algorithm according to an embodiment of the present invention, such as image 3 As shown, the first part is the output of the bottleneck process of the daily product order, in image 3 Including four production lines are A01, A05, A07, A08, production line A01 assembles two types of parts A and C, production line A05 assembles four types of parts B, W, C, T, production line A07 assembles A , B, W, C, D five types of parts, production line A08 assembles A, T two types of parts, the following four types of A, B, C, D parts are used as examples to illustrate, other types of...
PUM
Login to View More Abstract
Description
Claims
Application Information
- IPC
- G06Q10/04; G06Q10/06; G06Q50/04
- CPC
- Y02P90/30
- Inventors
- 尹兆兵; 张广平