Method for correcting deviation of building in miniature pile hole earth taking manner
A technology of buildings and micro-piles, which is applied in the direction of construction and infrastructure engineering, can solve the problems of heavy excavation workload, high risk, and easy to be restricted by site conditions, and achieve easy control, cost reduction, and rectification process precise effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] Such as figure 1 and 2 As shown, they are respectively the elevation and plan view of the building before the rectification. For this building, the method of rectifying the rectification of the building by taking soil from the micro-pile pile holes includes the following steps:
[0042] (1) Above the building foundation 3 on the larger side of the settlement, set up a drilling machine to drill the micro-pile pile holes 7; The hard soil layer 6 below; in order to prevent the hole from collapsing, the method of protecting the wall of the steel casing is adopted.
[0043] (2) if Figure 3-6 As shown, hang the reinforcement cage or steel pipe in the drilled hole and pour the cement mortar with the strength of M30 (M30 cement mortar-the mass ratio of water and cement is 0.5~0.6:1, the mass ratio of cement and sand is 1:0.3 ), and at the same time pull out the retaining wall steel casing; after the cement mortar pouring in the entire pile body is completed, the strength of...
Embodiment 2
[0050] Such as Figure 13 As shown, a frame structure residential building with 6 floors above ground and 1 floor below ground in Yantai has a highly compressible soil layer (from top to bottom: silty clay, silt, muddy silty clay, gravel sand) Mixed breccia and fully weathered mica schist), it dipped southward shortly after its completion, and the inclination rate exceeded the 0.4% standard allowed by the national code. In order to implement building tilt correction, the following steps are taken:
[0051] (1) Set up a drilling machine above the raft foundation on the larger settlement side (the southernmost side), and drill a row of miniature pile pile holes; the pile holes pass through silty clay, silt, silty silty clay, up to the underlying gravel-sand-mixed breccia; drill site see Figure 14 , the diameter of the pile hole is 220mm, the pile length is 15m, and the pile end enters the gravel-sand mixed breccia layer for 2.0m. In order to prevent the hole from collapsing,...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com