Restoration method for quarry in frozen soil region
A repair method and quarry technology, which is applied in the fields of land preparation methods, agricultural machinery and tools, construction, etc., can solve the problems of high backfill cost and difficulty in repairing quarries in permafrost areas, so as to reduce transportation costs and reduce Dosage, effect of mitigating effects
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] Embodiment 1: refer to Figure 1 to Figure 3 , a method for repairing quarries in permafrost regions disclosed by the present invention, comprising the following steps:
[0042] Step 1, clean up the waste rock 4 in the area of the quarry 1, pile it up in a centralized manner, and reserve it;
[0043] Step 2, making gabion cage 3, filling waste rock 4 in gabion cage 3, forming gabion gabion retaining wall 2, making two circles of gabion gabion retaining wall 2 arranged at intervals on the edge of quarry 1, The distance between the two circles of gabion retaining walls 2 is 1 meter, the edge planting area 5 is formed in the middle of the two circles of gabion retaining walls 2, and the area surrounded by the inner circle of gabion retaining walls 2 is the middle planting area 6. The gravel from the quarry 1 is used to make the gabion retaining wall 2, and the waste rock 4 is recycled to reduce costs. The gabion retaining wall 2 can also prevent soil erosion;
[0044]S...
Embodiment 2
[0047] Embodiment 2: A method for repairing a quarry in a permafrost region. The difference from Embodiment 1 is that the thickness of the first soil layer 9 is 30 cm, and the thickness of the second soil layer 10 is 70 cm. The height of cage retaining wall 2 is 80 centimetres.
Embodiment 3
[0048] Embodiment 3: A method for repairing a quarry in a permafrost region. The difference from Embodiment 1 is that the thickness of the first soil layer 9 is 80 cm, and the thickness of the second soil layer 10 is 20 cm. The height of cage retaining wall 2 is 30 centimetres.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com