Rapid treatment method for controlling ground surface settlement caused by stratum funnel of large-diameter shield construction

A technology of surface settlement and treatment method, which is applied in the field of rapid processing and control of surface settlement when large-diameter shield construction encounters a funnel in the ground. It can solve problems such as uneven settlement, achieve simple construction, increase the safety of construction personnel, and improve the properties.

Active Publication Date: 2020-11-03
CHINA RAILWAY 18TH BUREAU GRP CO LTD +1
View PDF10 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The purpose of the present invention is to effectively solve the problem of uneven settlement when large-diameter shield tunnels encounter stratum funnels, ensure the long-term safety and stability of ground buildings and underground shield tunnels, and speed up the construction process of shield tunnels passing through dense building groups

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Rapid treatment method for controlling ground surface settlement caused by stratum funnel of large-diameter shield construction
  • Rapid treatment method for controlling ground surface settlement caused by stratum funnel of large-diameter shield construction
  • Rapid treatment method for controlling ground surface settlement caused by stratum funnel of large-diameter shield construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0049] The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

[0050] The present invention provides a rapid treatment method for controlling ground surface and building settlement when a large-diameter shield construction encounters a funnel in the ground. The treatment technical process is shown in figure 1 . According to the construction characteristics and treatment significance, it can be divided into four major components: construction preparation work before reinforcement treatment, ground building grouting protection and reinforcement, tunnel and upper stratum funnel reinforcement, and reinforcement effect detection.

[0051] 1. The construction preparation work before the reinforcement treatment is as follows:

[0052] 101. Prove the s...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a rapid treatment method for controlling ground surface settlement caused by sudden stratum funnel of large-diameter shield construction. The method comprises the following steps of Exploring the range of the stratum funnel, investigating interval buildings, performing ground monitoring, reinforcing soil below the ground buildings through layer-by-layer deep hole grouting,performing pre-grouting reinforcement on a tunnel and the stratum funnel above the tunnel, and detecting the reinforcement effect. According to the steps, disturbed soil under the building is vertically drilled from the ground for layered grouting reinforcement, a water outlet channel at the bottom of the stratum funnel is sealed and blocked from bottom to top by adopting a grouting process, and besides, the reinforcement effect is inspected by combining multiple modes, so that the continuous safety and stability of the ground building and the tunnel are ensured. The method can solve the problem of ground surface settlement caused by the sudden stratum funnel of large-diameter shield construction, and overcomes the engineering difficulties of large constraint of early-stage exploration means and settlement damage of dense and old buildings on the ground caused by sudden unfavorable geology shield water inflow.

Description

technical field [0001] The invention relates to the field of controlling ground subsidence during shield construction, in particular to a rapid treatment method for controlling ground subsidence when large-diameter shield construction encounters a funnel in the ground. Background technique [0002] Urban subway shield tunnels often pass through dense clusters of old buildings, which has a significant impact on the original urban arterial roads, buildings, and underground structures. Due to the dense old buildings and shallow foundation buildings, the geological survey in the early stage is very limited, and the geological survey and drilling are often unable to cover the entire interval accurately. At this time, it is easy to encounter the formation funnel under the building when the shield passes through. . In general, the range of stratum funnels is relatively small, which belongs to the sudden change of terrain and geology. During the preliminary survey, it is difficult ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/00E21D9/06E21F17/00
CPCE21D9/001E21D9/002E21D9/003E21D9/0671E21F17/00
Inventor 李文广雷锋国刘洪亮高鹏张树凯彭光火焦叶飞郭佳李志伟李祥龙王金成李成伟绳鹏程郑林孟海通夏宁斌
Owner CHINA RAILWAY 18TH BUREAU GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products