Super high-rise building structure dismounting and changing construction method and checking method

A technology of building structure and construction method, which is applied in the direction of building structure, construction, building maintenance, etc., can solve the problems of high difficulty and low efficiency in the demolition and modification of super high-rise building structures, so as to improve the efficiency of demolition and modification, reduce the difficulty of demolition and modification, The effect of saving disassembly and modification time

Active Publication Date: 2022-03-08
CCFED THE FIRST CONSTR & ENG +1
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art, and provide a super-high-rise building structure demolition construction method and checking method, which is mainly used to solve the difficulty and efficiency of super-high-rise building structure demolition in the prior art. low level problem

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Super high-rise building structure dismounting and changing construction method and checking method
  • Super high-rise building structure dismounting and changing construction method and checking method
  • Super high-rise building structure dismounting and changing construction method and checking method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0072] Refer Figure 5 In order to meet the structure of the structure, the structural removal construction process, the anti-side stiffness, carrying capacity requirements, while shortening the construction period, through finite element modeling analysis and wind tunnel test argument, the total 46-storey ultra-high-rise building structure structure Divided into 9 construction segments, namely n equals 46, m equal to 9, transformed from top and down construction, 6 floors per segment of the top five construction segments, start from the sixth construction section to the ninth construction section, each layer Decreasing paralycenes, 5 floors, 4 layers, 3 floors, 2 layers, namely a equal to 3. Due to the new construction of 12M across steel steel beam, there is no need to set up vertical components. When the construction section is completed, the new two-layer party needs to continue to dismantle, each paragraph is removed from the top, and the construction is removed. In addition, ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a super high-rise building structure dismantling and changing construction method and a checking method. The construction method comprises the steps that construction segmentation is conducted on a building structure comprising N layers of floor structures; pre-determining a to-be-dismantled structure and a to-be-newly-built structure for each floor structure; each construction section is constructed from top to bottom from the first construction section until construction of the Mth construction section is completed; the construction in each construction section comprises the steps of dismantling a to-be-dismantled structure from top to bottom and reconstructing a to-be-newly-built structure from bottom to top; and before the nth construction section is constructed, the reconstruction progress of at least one construction section in the previous construction sections is judged, and the nth construction section is constructed according to the judgment result. The checking method comprises the steps that the division number of construction sections and the floor structure included in each construction section are determined; determining the most unfavorable construction condition for each construction section; and checking the overall structural rigidity of the building structure and the bearing capacity of the corresponding component under the most unfavorable construction condition. The rigidity is ensured to meet the requirement, the safety is improved, and the dismounting difficulty is reduced.

Description

Technical field [0001] The present invention belongs to the field of construction construction technology, and more particularly to the demolition and reform construction method of ultra-high-layer building structure and the method of checking. Background technique [0002] With the improvement of people's living standards, scientific and technological progress and the improvement of construction technology, and there are more and more large-scale large-scale buildings, and higher requirements for super high-rise buildings. Since the land is a non-renewable resource, the construction of a conservation society does not allow unlimited flooring to occupy a large number of cultivated land engaged in construction, the maintenance and reinforcement of old buildings, the maintenance of old buildings, and the expansion application is one of the inevitable choices of urban construction, through the building Reinforcement transformation to increase, expand, change the use, so that old bui...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04G23/08E04G23/02
CPCE04G23/08E04G23/0218
Inventor 周贞勇苏东颖王金伟王媛王坤
Owner CCFED THE FIRST CONSTR & ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products