Database-based railway mountain tunnel construction organization design method

A technology of tunnel construction and design method, which is applied in database index, database management system, data processing application, etc., can solve the problem of inability to consider the construction direction of import and export, auxiliary tunnel construction direction, tunnel opening construction preparation period, winter break, and roof entry. The delay of the secondary lining in the construction period, the inability of the railway tunnel auxiliary design system to realize the intelligent design of the construction organization, the low design speed and efficiency, etc., achieve the effect of reducing the cost of learning and use, lowering the threshold for professional knowledge requirements, and realizing the accumulation of design experience.

Pending Publication Date: 2022-07-19
CHINA RAILWAY DESIGN GRP CO LTD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

There are three shortcomings in the traditional design method: first, the design process is cumbersome, the repetitive workload is heavy, and the later modification workload is heavy; second, the design speed and efficiency are low; third, human matching errors are prone to occur
[0003] None of the currently known auxiliary design systems for railway tunnels can realize the intelligent design of construction organization. They can only complete the simple matching and design of construction progress indicators in a specific situation, and cannot consider the construction direction of entrance and exit, the construction direction of auxiliary tunnels, and the construction of openings. Combination of multiple factors such as preparation period, winter break period, construction period of roof-lifting, secondary lining lag, secondary attack direction lag, etc.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Database-based railway mountain tunnel construction organization design method
  • Database-based railway mountain tunnel construction organization design method
  • Database-based railway mountain tunnel construction organization design method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0085] Step A, according to the tunnel design principle of the railway project in the embodiment, establish a construction progress index database, such as figure 2 . Among them, the database applicable conditions include "general applicable conditions" and "special applicable conditions".

[0086] Step B, according to the mechanization supporting situation of the railway project in the embodiment, the applicable mileage range of the mechanization supporting input in the technical standard is CK80+000~CK250+000; the database applicable conditions of the railway project in the embodiment are all "generally applicable". "Conditions", only special applicable conditions need to be entered here, and all the mileage parts that are not entered are all defaulted to "general applicable conditions", so they can be omitted here, such as image 3 .

[0087]Step C, input the construction parameters of the tunnel in the embodiment, the tunnel is "dual line", the import construction prepa...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a database-based railway mountain tunnel construction organization design method, which comprises the following steps of: respectively establishing construction progress index databases for different types of railway mountain tunnels; inputting applicable mileage ranges of different construction progress index parameters in the technical standard; reading construction parameters of the main tunnel and the auxiliary tunnel; matching and generating a construction progress index of the construction of the auxiliary tunnel, and calculating the construction time of the auxiliary tunnel; matching and generating a construction comprehensive information table of the main tunnel; dividing work areas, generating a work area information table, and generating an effective work area group table; calculating the through mileage, the through construction period and the total construction period of each work area; a calculation result is extracted, and a construction organization information table is generated; and generating fixed format data convenient for drawing a tunnel construction organization diagram. The intelligent design of the construction organization of the railway mountain tunnel under various combination conditions is realized. The design difficulty is reduced, the design efficiency is improved, the universality is high, and the flexibility is high.

Description

technical field [0001] The invention belongs to the technical field of railway mountain tunnel design, in particular to a database-based construction organization design method for railway mountain tunnels. Background technique [0002] The construction organization design of the railway mountain tunnel is an important link in the design of the railway mountain tunnel, which plays a key role in the comparison and selection of the scheme and the control of the construction period. When using the traditional design method, the designer needs to manually select the construction progress indicators of each section of the main tunnel and auxiliary tunnel one by one, and cooperate with manual calculation. The total construction period can be calculated after drawing a map. The traditional design method has three shortcomings: first, the design process is cumbersome, the repetitive workload is large, and the later modification workload is large; second, the design speed and efficie...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06F16/25G06F16/22G06Q10/06G06Q50/08
CPCG06F16/252G06F16/2282G06Q10/06393G06Q10/06313G06Q50/08
Inventor 苏伟吴迪傅安民廖立坚李艳夏勇侯军红张兴华白青波刘龙王雨权杨智慧贾辉陈浩然
Owner CHINA RAILWAY DESIGN GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products