Pre-splitting Blasting Method of Negative Excavation Ring Corridor in Nuclear Island
A technology of pre-splitting blasting and ring gallery, which is applied in blasting and other directions
- Summary
 - Abstract
 - Description
 - Claims
 - Application Information
 
 AI Technical Summary 
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0024] The plane of the nuclear island ring corridor in this embodiment is as follows figure 1 As shown, the ring corridor is located between the inner ring N of the island center with a radius of 15.3m and an elevation of minus 10.23m and the outer ring W of an elevation of minus 10.15m, with a width of 5.5m and an elevation of minus 13.38m. The steps of pre-splitting blasting are:
[0025] The first step is to dig down to negative 9.23m rock foundation at the selected location according to the elevation of the island center, and reserve a 1m reserve layer. Practice shows that the flatness of the upper part of the pre-splitting surface is poor. In order to ensure the integrity of the upper profile of the ring corridor of the nuclear island, a reserve layer of about 1m should be reserved during the pre-splitting blasting of the ring corridor.
[0026] Step 2. Along the inner and outer circumferences of the ring corridor (that is, the inner and outer rings) at equal intervals ...
PUM
 Login to View More Abstract
Description
Claims
Application Information
 Login to View More - R&D
 - Intellectual Property
 - Life Sciences
 - Materials
 - Tech Scout
 
- Unparalleled Data Quality
 - Higher Quality Content
 - 60% Fewer Hallucinations
 
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com