Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel

A technology of multi-arch tunnel and construction method, which is applied in the direction of tunnel, tunnel lining, earthwork drilling and mining, etc., to achieve the effect of small settlement, increase the construction working face, and reduce the risk of rockburst

Inactive Publication Date: 2010-06-16
POWERCHINA HUADONG ENG COPORATION LTD
View PDF0 Cites 40 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The technical problem to be solved by the present invention is to provide a construction method for rebuilding and expanding an existing single-hole tunnel into a double-arch tunnel in view of the problems existing in the reconstruction and expansion of existing tunnels. The construction plan of the pilot pit increases the construction surface to achieve the purpose of reducing the excavation surface and disturbing the surrounding rock range, and improving the construction safety

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
  • Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] Such as figure 1 As shown, this embodiment considers the background of expanding a single-hole, two-way, two-lane tunnel into a two-way, four-lane multi-arch tunnel. The existing single-hole tunnel 34 has a clear width of about 9m, a clear height of about 5.5m, and a building boundary height of about 3m. According to relevant norms and technical standards, the clearance limit of the existing single tunnel 34 cannot meet the requirements, and reconstruction and expansion are urgently needed. Due to the limitation of the wiring conditions at both ends of the tunnel, it is determined to make full use of the existing single-hole tunnel when drawing up the construction plan. The design has been repeatedly demonstrated in terms of safety, economy, and construction period, and a construction plan for three pilot pits of "pilot tunnel in construction + combination of existing single tunnel + construction of right tunnel" was proposed. The plane layout of the new multi-arch tu...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a method for constructing a double-arch tunnel by rebuilding and expanding an existing single-hole tunnel. The technical problem to be solved by the invention is to provide a method for constructing the double-arch tunnel by rebuilding and expanding the existing single-hole tunnel, which adopts a ' middle pilot hole, the existing tunnel and a right hole' three pilot pit construction scheme, enlarges construction face and reduce excavation face and surrounding rock disturbed zone. To solve the technical problem, the invention adopts a technical scheme that the method for constructing the double-arch tunnel by rebuilding and expanding the existing single-hole tunnel comprises the following steps: 1.1 constructing the middle pilot hole parallel to the existing single-hole tunnel on one side of the existing single-hole tunnel and completing supporting construction; 1.2, constructing a left hole by sequence and zone on the basis of the existing single-hole tunnel and communicating the left hole and the middle pilot hole; and 1.3, after excavating the left hole to a certain size, constructing the right hole by sequence and zone and communicating the right hole with the middle pilot hole. The method is mainly used in highway traffic engineering and municipal traffic engineering.

Description

technical field [0001] The invention relates to a construction method for rebuilding and expanding an existing single-hole tunnel into a multi-arch tunnel. It is mainly applicable to highway traffic engineering and municipal traffic engineering. Background technique [0002] With the rapid development of our country's national economy, the traffic volume is increasing day by day, and some existing roads can no longer meet the requirements of transportation, and need to be rebuilt and expanded to achieve the corresponding service level. In economically developed areas, these problems have become increasingly prominent, such as the reconstruction and expansion of Shenyang-Dalian Expressway and Shanghai-Hangzhou Expressway. With the continuous development of highways and municipal infrastructure, the tunnel project has been developed rapidly. The tunnel has developed from a single tunnel for two-way driving to a double tunnel for uplink and downlink separation. Regardless of ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E21D9/14E21D9/06E21D11/04
Inventor 章立峰邹金杰吴向东吾佳
Owner POWERCHINA HUADONG ENG COPORATION LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products