Handling method of province-level power grid black-start and large-range power failure accidents
A provincial power grid and accident handling technology, applied in the field of power system, can solve problems such as system collapse, complex and variable availability of power transmission and transformation equipment, and load recovery impact, etc., and achieve the effect of formulating a scientific system
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0034] The detailed simulation calculation and analysis of the black start process of the black start scheme of the Leiyang Plant by the Hunan Dongjiang Unit via the long-distance high-voltage line is carried out. The calculation report is as follows:
[0035] 1) Self-excitation calibration: The self-excitation problem of the unit is a resonance phenomenon. When the length of the transmission line increases, the capacitive reactance XC of the line becomes smaller. If XCXd+XT, self-excitation does not occur, On the contrary, a self-excitation phenomenon occurs. In this scheme, the Dongjiang generator set empty-charges the 220kV busbar of the Leiyang plant via the long-distance high-voltage line:
[0036] Xd+XT=0.5947+0.0853=0.68 (per unit value),
[0037] Bc=2*(0.018682+0.056+0.004446)=0.158
[0038] XC=6.32 (per unit value),
[0039] XC>>Xd+XT, so self-excitation will not occur.
[0040] 2) Power frequency overvoltage verification: The total length of the power transmissi...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com