Construction method of upper structure of steel-concrete overlapping beam

A construction method and technology of laminated beams, applied in bridges, bridge construction, erection/assembly of bridges, etc., can solve problems such as high cost, difficulty in ensuring construction quality, complicated operation, etc., and achieve low cost, fast construction, and wide application range Effect

Active Publication Date: 2015-04-22
CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP OF THE FIFTH ENG +1
View PDF4 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Among them, the steel-concrete composite beam system is a bridge system that has been widely used in recent years. However, the existing construction methods for steel-concrete composite beams are difficult to guarantee the construction quality, and the cost is high and the operation is complicated, which delays the construction progress to a certain extent.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0033] The present invention will be further described in detail below in conjunction with examples, but the embodiments of the present invention are not limited thereto.

[0034] A construction method for the upper structure of a steel-concrete composite beam, according to the structural characteristics, size and other design requirements of the construction composite beam, as well as various conditions on the construction site, the following construction process is adopted;

[0035] For construction preparation, before the construction unit starts construction, the on-site construction plan and implementation construction organization design should be prepared and submitted for approval according to the design documents, drawings, construction conditions, project progress, etc. And check the drawings carefully. The construction section division of the main girder, the location and structure of the lifting point are determined by the construction unit according to the stru...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method of an upper structure of a steel-concrete overlapping beam. The method includes the following steps of erection of flexible temporary buttresses, mounting of supporting seats, mounting of pre-embedded parts, hoisting of steel beams, fine adjustment of the beams, beam section welding, first-time removing of supports, pouring of bridge deck slab sections, prestress tension, second-time beam lowering and removing of the flexible temporary buttresses. According to the construction method of the upper structure of the steel-concrete overlapping beam, the construction process of erection of the steel beams and a large-tonnage steel beam fine adjustment device by means of a flexible buttress method has the advantages of convenient operation, fast construction and the like, devices that are used in the construction method are common devices that are made of common materials and can be applied to common bridge construction sites, costs are low, and the application range is wide.

Description

technical field [0001] The technical field of building construction of the present invention specifically refers to a construction method for the superstructure of steel-concrete composite beams. Background technique [0002] With the development of society and the progress of economy, there are more and more bridge projects, and at the same time, bridge engineering has gradually become one of the important factors to promote my country's economic development. Among them, the steel-concrete composite beam system is a bridge system that has been widely used in recent years. However, the existing construction methods for steel-concrete composite beams are difficult to guarantee the construction quality, and the cost is high and the operation is complicated, which delays the construction progress to a certain extent. . Contents of the invention [0003] The object of the present invention is to provide a construction method for the superstructure of steel-concrete com...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00
CPCE01D21/00
Inventor 李海云张庆丁浩航何十美
Owner CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP OF THE FIFTH ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products