Counter weight control construction method for large span un-symmetric segment stayed-cable bridge
A construction method and technology for cable-stayed bridges, applied to cable-stayed bridges, bridges, bridge forms, etc., can solve the problems of tower top deviation and inability to better control the beam line shape, so as to correct tower deflection and reduce construction effect of load
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0033] Such as figure 1 , figure 2 Shown, the large-span asymmetric section cable-stayed bridge of construction of the present invention is the asymmetrical reinforced concrete cable-stayed bridge of single tower double cable plane, and the hole span layout position of this cable-stayed bridge is 208m+270m+35m+30m and its main span It is 270m. That is to say, the distance between the cable tower 1 arranged on the side span pier and the left side span side pier 5 is 208m, and the distance between the cable tower 1 and the right main span side pier 7 is 270m. The distance between the main span side pier 7 and the abutment 13 on the right side is 35m+30m, and a pier 14 is also arranged between the main span side pier 7 and the abutment 13, between the main span side pier 7 and the abutment 14 The distance between the pier 14 and the abutment 13 is 30m. The main span beam section that has been constructed has been erected between the main span side pier 7 and the abutment 13, ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com