Construction method of large-volume concrete bearing platform with one-time pouring in winter
A large-volume concrete and construction method technology, which is applied in the direction of construction, building structure, and building material processing, can solve the problems of large concrete temperature gradient, reduce the service life of the structure, and affect the safety of the structure, and achieve good temperature difference control effect. The effect of good quality and low investment cost
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2010-07-21
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the technical field of large-volume concrete pouring construction in winter, and in particular relates to a one-time pouring construction method for large-volume concrete caps in winter. Background technique
[0002] Daijiawan Weihe Bridge in Baoji City is 1146 meters long, and the span combination: 10×20 meters (hollow slab girder) + 127 meters (cable-stayed bridge) + 16×32 meters (large hole slab beam) + 127 meters ( Cable-stayed bridge) + 9×20 meters (hollow slab girder), the main bridge is a cable-stayed structure with a single tower and no back cables. There are two bridges in total, crossing the Xibao Expressway and the planned Binhe Road respectively. The total length of the cable-stayed bridge is 127 meters, the specific span layout is 32+75+20 meters, the main tower is 63 meters long above the bridge deck, and 10.425 meters below the bridge deck. The beam is 28 meters wide, and 9 fan-shaped stay cables are installed t...
Examples
Embodiment Construction
[0044] Such as figure 1 A one-time pouring construction method for large-volume concrete caps in winter includes the following steps:
[0045] Step 1. Binding of reinforcement cages: according to the designed structure and size of the large-volume concrete cap 4 to be formed, the reinforcement cage for forming the large-volume concrete cap 4 is bound on the construction platform.
[0046] Step 2. Arrangement of cooling water pipes and temperature measuring elements: After the reinforcement cage is bound or during the binding process, a multi-layer circulating cooling water pipe 1 is horizontally laid out in layers inside the steel cage, and the inlet of the circulating cooling water pipe 1 The water inlet and the water outlet are led out from the top of the steel cage through the water inlet pipe 2 and the water discharge pipe 3 respectively, and then lead into the sump respectively. The deployed temperature measuring elements include a temperature measuring element 5-1 for r...