Method for defining and calculating compaction and settlement ratio so as to determine optimal compaction times
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- ZHONGBEI UNIV
- Publication Date
- 2014-10-01
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention defines and calculates the tamping-sink ratio to determine the optimal tamping number, belongs to the technical field of civil engineering foundation treatment, and specifically relates to the efficiency transformation of a tamping hammer. Background technique
[0002] The dynamic compaction method is a method of freely dropping a weight of tens of tons (generally 8-40t) from a height of tens of meters (generally 6-40m) to compact and strongly compact the foundation soil. The current situation is that the practice of dynamic compaction is developing rapidly, but there are still many ambiguities in the mechanism and design theory of dynamic compaction. The theory is far behind the practice. Issues such as energy distribution and construction optimization of dynamic compaction have always attracted attention.
[0003] At present, conventional methods for determining the number of ramming include the empirical method, the method of determini...