Unified data center management system and management method thereof
A technology of data center and management method, applied in the direction of digital transmission system, transmission system, data exchange network, etc., can solve the problems of low effective utilization of resources and high energy consumption, so as to improve the low utilization rate of resources, ensure reasonable utilization, The effect of reducing energy consumption
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0074] Please refer to figure 1 , figure 1 It is a flowchart of a unified data center management method provided by an embodiment of the present invention. The management method of this embodiment includes:
[0075] Step 101: basic information management;
[0076] Step 102: resource planning management, including physical resource planning, virtual resource planning and system planning;
[0077] Step 103: resource management, including computing resource 1031, network resource management 1032, storage resource management 1033 and topology presentation 1034;
[0078] Step 104: process management, including resource application 1041 and application query 1042;
[0079] Step 105: Operation and maintenance management, including system image management 1051, system patch management 1052, system parameter management 1053, and audit management 1054;
[0080] Step 106: task management;
[0081] Step 107: resource optimization, including resource allocation optimization, energy co...
Embodiment 2
[0091] Please refer to figure 2 , figure 2 It is a flow chart of the resource planning management method provided by the embodiment of the present invention. The resource planning management method of this embodiment includes:
[0092]Step 2021: Physical resource planning, by defining a resource on-shelf plan, automatically generating on-shelf detection tasks and automatically sensing resource status, when resources are powered on, resource hardware information can be automatically collected and saved, realizing resource collection on bare devices;
[0093] Step 2022: virtual resource planning, through virtual resource planning, automatically build the required virtual resource environment and incorporate it into the resource management system;
[0094] Step 2023: system planning, used to plan the operating system configuration of the computing device, and use the generated configuration file for physical machine installation and virtual machine image production.
Embodiment 3
[0096] Please refer to image 3 , image 3 It is a flow chart of the task management method provided by the embodiment of the present invention. The task management method of this embodiment includes:
[0097] Step 3061: Physical machine installation, through the development of mirror images and system planning configuration files, to realize automatic batch installation of physical machine operating systems;
[0098] Step 3062: create a virtual machine, realize automatic batch creation of virtual machines by formulating image and virtual machine specifications;
[0099] Step 3063: virtual machine destruction, used to realize batch destruction of virtual machines;
[0100] Step 3064: physical resource inspection, used to realize the automatic inspection function of physical resources, and detect whether there is a problem inside the physical resource hardware;
[0101] Step 3065: Virtual resource inspection, used to realize the automatic inspection function of virtual resou...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com