Unprotected open cut excavation subway station shield launching and receiving end backfill and reinforcement method
A technology for subway station and grading excavation, which is applied to filling, underwater structures, infrastructure engineering, etc., and can solve problems such as long construction period, cumbersome procedures, and difficulty in controlling the quality of backfill reinforcement
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2020-07-10
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of subway construction, and specifically refers to a method for backfilling and reinforcing the starting and receiving ends of shield tunnels in grading and excavating subway stations. Background technique
[0002] In the shield construction technology, before the departure and reception of the subway car with the enclosure structure, it is generally necessary to reinforce the end first, and only after meeting the requirements of the bearing capacity of the foundation and the stability of the soil passing through the stratum can the The next step is construction.
[0003] Before the start and reception of the excavated subway station by grading, the two sides of the station structure are foundation pits, which cannot be reinforced by the conventional method. At present, there are two common construction schemes: the first one is to backfill plain soil by layered rolling, and then carry out conventional ground reinfor...
Examples
Embodiment Construction
[0024] combined with Figure 1~4 , the method for backfilling and reinforcing the starting and receiving ends of shield tunnels in grading excavation for subway stations includes the following steps:
[0025] (1) Backfill range measurement: carry out actual measurement to determine the backfill range;
[0026] (2) Backfill in the portal area: at the end of the foundation pit, backfill in different areas, specifically, backfill plain concrete 1 with one tunnel diameter along the tunnel direction, backfill cement soil 2 with one tunnel diameter to the foot of the slope, and fill to the 1m above the entrance;
[0027] (3) Manufacture and installation of steel pipe pile embedded parts: after backfilling the end area, install the embedded part 3 along the preset position. The embedded part 3 includes a square steel plate 301, and several L Type steel bar 302;
[0028] (4) Anti-floating pressure plate construction: pour a cushion on the surface of the backfill, and bind the steel...