Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

A construction method of a temporary collection station for plain river garbage

A construction method and technology for a collection station, which are applied to the construction field of a temporary collection station for river waste in plains, can solve the problems of difficult re-use of demolition, high requirements on geological conditions, and high labor intensity, and achieve easy and flexible layout, low construction cost, Sturdy structure

Active Publication Date: 2022-04-15
SINOHYDRO FOUND ENG
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Most of the existing temporary garbage collection stations are built with bricks, masonry or concrete and other materials, which have complex construction techniques, high construction difficulty, high labor intensity, long project period, high construction cost, high requirements on geological conditions, and dismantling. Difficult to reuse and other disadvantages

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method of a temporary collection station for plain river garbage
  • A construction method of a temporary collection station for plain river garbage
  • A construction method of a temporary collection station for plain river garbage

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0049] Such as Figure 1 to Figure 13 Shown, be the construction method of a kind of plain river course rubbish temporary collection station of the present invention, comprise the steps:

[0050] (a) Foundation construction: the foundation support frame 1 includes a first steel bar 2 and a second steel bar 3, the first steel bar 2 is symmetrically distributed with positioning through grooves 4, and the first steel bar 2 is provided with a first groove 5 With the first screw hole 6, the two sides of the second steel bar 3 are provided with positioning columns 7 corresponding to the positioning through groove 4, and the second steel bar 3 is provided with a second groove 8 and a second screw hole 9 to support The bottom of the bottom plate of the steel column 10 is provided with a post 11, the top plate of the supporting steel post 10 is provided with a fixed through-slot 12 corresponding to the post 11, and the first steel bar 2 is provided with a fixed opening corresponding to...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for a temporary garbage collection station in a plain river course, which comprises the following steps: (a) building a foundation; (b) building a side wall; and (c) capping. The invention has simple process, step-by-step order, sufficient operation space, positioning operation, low construction difficulty, high construction efficiency, easy control of construction quality, low manual labor intensity, ensuring the assembly quality of the temporary garbage collection station, and the temporary collection of garbage The capacity of the station can also be flexibly adjusted according to actual needs, with strong adaptability, can be dismantled and transferred to other places for continued use, and has high resource utilization.

Description

technical field [0001] The invention belongs to the technical field of plain river garbage collection, and in particular relates to a construction method for a temporary plain river garbage collection station. Background technique [0002] In the plain river improvement project, it is necessary to transport the collected garbage to the designated area for temporary storage. Under the open-air storage, the odor generated by the garbage wafts around, and the garbage leachate flows around, which seriously affects the surrounding environment. Therefore, a temporary garbage collection station is set up. to pile up the rubbish. Most of the existing temporary garbage collection stations are built with materials such as bricks, masonry or concrete, which have complex construction techniques, high construction difficulty, high labor intensity, long project period, high construction cost, high requirements on geological conditions, and dismantling. Difficult to reuse and other disadv...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04H7/00E04H7/30E03F1/00E03F5/14B65F5/00
CPCE04H7/00E04H7/30E03F1/00E03F5/14B65F5/00
Inventor 郭万红李云松李永兵韩兵刘学应任二伟金益刚黄晓勇赵攀峰刘发奎
Owner SINOHYDRO FOUND ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products