[0041] A sealing process for hazardous solid waste, comprising the steps of:
[0042] Step S1: providing a sealing site 1, pouring 8-10 cm foam concrete on the surface of the sealing site 1 to form a first foam concrete layer 2;
[0043] Step S2: Provide the following raw materials: hazardous solid waste, gelling material, water and foaming agent, prepare the hazardous solid waste, gelling material, water and foaming agent into slurry, and cast in-situ to obtain discontinuous The foam concrete block 3 is sealed once;
[0044] Step S3: pouring 5-10 cm of foam concrete around the foam concrete block 3 and its top to form a second foam concrete layer 4, and the first foam concrete layer 2 is connected to the second foam concrete layer 4 The foam concrete block 3 is subjected to secondary sealing.
[0045] Wherein, the first foamed concrete layer 2 and the second foamed concrete layer 4 are both cast-in-place by conventional foamed concrete, and the foamed concrete does not cont...
Embodiment 2
[0049] This embodiment provides a sealing process for hazardous solid waste, which is different from Embodiment 1 in that:
[0050] The parts by weight of the hazardous solid waste, gelling material, water and foaming agent are: 400 parts, 120 parts, 150 parts and 3 parts in sequence.
[0051] Specifically, the hazardous solid waste is red mud; the cementitious material is cement; and the foaming agent is HTW-1 vegetable protein composite foaming agent.
Embodiment 3
[0053] This embodiment provides a sealing process for hazardous solid waste, which is different from Embodiment 1 in that:
[0054] Both the first foam concrete layer 2 and the second foam concrete layer 4 are formed by cast-in-place foam concrete, and the foam concrete does not contain hazardous solid waste.
[0055] The parts by weight of the hazardous solid waste, gelling material, water and foaming agent are: 700 parts, 250 parts, 200 parts and 4 parts in sequence.
[0056] Specifically, the hazardous solid waste is red mud; the cementitious material is cement; and the foaming agent is HTW-1 vegetable protein composite foaming agent.
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 