Reignition method for base aluminum groove
A secondary start-up and aluminum tank technology, applied in the field of secondary start-up of aluminum tanks, can solve problems such as leaky tanks, anode depolarization, and reduced life of electrolytic cells
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0009] Take the 300kA aluminum electrolytic cell as an example.
[0010] After the electrolytic cell is powered off and the cell is shut down, clean up the electrode material and the aluminum block in the cell, repair the electrolytic cell, and perform conventional furnace loading and roasting; within 23 hours after the start-up, the roasting is transferred to the electrolytic cell After pouring aluminum liquid, the voltage rises to 6V within 2 hours of pouring aluminum liquid; after 2 hours after pouring aluminum, the voltage is uniformly reduced from 6V to 4.5V; within the next 24 hours, the control voltage is uniformly reduced from 4.5V to 4.3V; reduce the voltage evenly to 4.2V within 24-48 hours; reduce the voltage to 4.18V evenly within 48-72 hours; reduce the voltage to 4.16V evenly within 72-96 hours Keep 4.10V, and then enter the post-management. During the start-up process, the furnace side is formed rapidly, and there is no large area of redness on the side carbo...
Embodiment 2
[0012] Take the 350kA aluminum electrolytic cell as an example.
[0013] After the electrolytic cell is powered off and the cell is shut down, clean the electrode material and the aluminum block in the cell, repair the electrolytic cell, and carry out conventional furnace charging and roasting; within 24 hours after the start-up, the roasting is transferred to the electrolytic cell After pouring aluminum liquid, the voltage rises to 6.5V within 3 hours of pouring aluminum liquid; after 3 hours after pouring aluminum, the voltage is uniformly reduced from 6.5V to 4.8V; within the next 24 hours, the voltage is controlled from 4.8V Reduce the voltage evenly to 4.5V; within 24-48 hours, reduce the voltage evenly to 4.3V; within 48-72 hours, reduce the voltage evenly to 4.2V; within 72-96 hours, reduce the voltage evenly to 4.18V, 96-120 The hourly voltage remains at 4.16V, and then enters post-management. During the start-up process, the furnace side is formed rapidly, and there ...