Construction method of bottom foundation architecture of large desulfurization anti-corrosion case and tank
A technology of basic structure and construction method, applied in basic structure engineering, construction and other directions, can solve the problems of difficult to control flatness error, high labor intensity, affecting the quality of anti-corrosion lining, etc. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0015] Combine the following figure 1 and figure 2 The present invention is further described.
[0016] The construction method of the foundation structure at the bottom of a large-scale anti-corrosion tank is characterized in that the steps are:
[0017] a) According to the width requirements of the steel floor 6 to be laid, pre-embedded screw rods 1 are arranged in pairs, directly welded on the foundation steel bars, and after checking that the angle and elevation are correct, the concrete foundation is poured to fix the position of the pre-embedded screw rods 1;
[0018] b) An upper nut 4 and a lower nut 2 are placed at the end of the exposed part of the pre-embedded screw 1, and an adjustment steel plate 3 is placed between the upper nut 4 and the lower nut 2, and the height of the lower nut 2 is finely adjusted in turn until the adjustment The height of the upper surface of the steel plate 3 meets the technical requirements of the drawings, the lower nut 2 and the pre-...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 