Method and system for solving voltage instability by cooperating with DC frequency modulation and low voltage load shedding

A low-voltage load shedding and frequency modulation technology, applied in the direction of AC network voltage adjustment, power network operating system integration, information technology support systems, etc. The effect of improving the stable operation level

Active Publication Date: 2015-09-23
CHINA ELECTRIC POWER RES INST +1
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

But for the weak receiving end power grid of small systems, after the low-voltage load shedding device operates to cut off the load, the system has a surplus of active power, which solves the problem of voltage stability and introduces the problem of frequency stability at the same time. The low-voltage-high-cycle-low-cycle problems are coupled together , the controllability of the system is relatively poor; if the system frequency increases greatly, it may cause the system to cut off the machine at high frequency, resulting in a large oscillation or even loss of stability of the power grid

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method and system for solving voltage instability by cooperating with DC frequency modulation and low voltage load shedding

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0033] Embodiment 1: A method for solving voltage instability at the receiving end with DC frequency modulation and low-voltage load shedding, the method includes the following steps:

[0034] (1). The DC receiving end system encounters a serious failure;

[0035] (2). Parallel judging whether the system reaches the set value of the low-voltage load shedding action and the DC frequency modulation action, and if so, enter steps (3) and (4), otherwise enter step (5);

[0036] (3). If the system voltage reaches the set value of the low-voltage load shedding action, then perform the low-voltage load shedding action to remove the load and enter step (5);

[0037] (4). If the system reaches the fixed value of the DC frequency modulation action, then perform the operation of DC frequency modulation action to adjust the power, and enter step (5);

[0038] (5). Determine whether the system voltage and frequency are restored, and if the system voltage or frequency fails to restore stab...

Embodiment 2

[0042] Example 2: A receiving end system is a weak AC power grid, and a large proportion of power is received from the main grid in DC bipolar operation. Taking the receiving power grid as an example, the effectiveness of using DC delay blocking as the three lines of defense to solve the problem of voltage stability is analyzed.

[0043] Such as figure 1 As shown, the analysis method is realized through the following steps:

[0044] Step 1: The initial working condition is that the DC power ratio of the weak receiving end system is 53%, which meets the N-1 check.

[0045] Step 2: A single-circuit, three-permanent-jump, and double-circuit fault occurred on the outgoing line of a supporting power plant in the system, and the voltage continued to drop and could not be recovered.

[0046] Step 3: The DC system detects that the system frequency is within the normal range, and the frequency modulation does not operate; the system low-voltage load shedding detection voltage reaches...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a method and system for solving voltage instability through direct-current frequency modulation and low-voltage load shedding coordination. The problems of voltage instability and 'low voltage and high circle' after a power grid at a small-direct-current and weak-system receiving end has a severe fault can be solved through the method by verifying through time-domain simulation analysis; the problem of leading in frequency stability can be avoided when the problem of the voltage stability can be solved by sufficiently realizing a rapid power adjusting function of a direct-current system; and voltage and a frequency signal of the system can be respectively detected by a voltage-voltage load shedding device and direct-current frequency modulation without coordination control, so that the high reliability and the simpler fixed value setting can be realized. The method and the system provided by the invention can be applied to planning and operation of a power system, and is beneficial to reasonably configuring a control measure of a third defense line of the power grid through system analysts, so that the stable operation level of the power grid at the small-direct-current and weak-system receiving end can be improved.

Description

technical field [0001] The invention belongs to the field of power systems, and in particular relates to a method and a system for solving voltage instability by coordinating DC frequency modulation and low-voltage load shedding. Background technique [0002] HVDC technology has the advantages of flexible power adjustment and no constraints on synchronous operation of the two-terminal system. On the one hand, it is widely used in long-distance and large-capacity power transmission occasions, and plays an important role in the national power grid interconnection; on the other hand, in It is also widely used in power transmission to small systems with weak AC grids. [0003] According to actual operating experience, when the weak receiving end grid receives power through a large proportion of DC, voltage stability problems are prone to occur. The failure of the AC system at the receiving end often causes commutation failure in the DC system, and the absorbed reactive power fu...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): H02J3/14
CPCY04S20/222Y02B70/3225
Inventor 罗煦之赵兵徐式蕴
Owner CHINA ELECTRIC POWER RES INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products