Underground water control method for backfilled sediment layer
A control method and groundwater technology, applied in construction, infrastructure engineering and other directions, can solve the problems of many obstacles, strong water permeability, foundation pit excavation and construction cannot be carried out, etc., to achieve the effect of simple process principle and ease of land use tension
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0017] The present invention is further illustrated below by specific examples.
[0018] Such as figure 1 , figure 2 Shown, a kind of groundwater control method of backfilling slag inclusion soil layer, comprises the following steps:
[0019] Step 1. Measure and locate around the excavation area of the foundation pit, set the groundwater control dam body excavation mark, and set out the line;
[0020] Step 2, excavating the dam body;
[0021] specifically,
[0022] Step 2.1, excavating a section of the dam body along the predetermined position,
[0023] Step 2.2, one end in the excavation section is provided with a drainage pump to remove the collected water in the excavation section of the dam body;
[0024] Step 2.3, filling the other end of the excavation section with clay for compaction, and so on to form the entire dam body 1;
[0025] Step 3, while excavating the dam body 1, pre-bury the downfall pipe well 2 beside the dam body, wherein, when backfilling the dam...