A connection method for prefabricated concrete pipe gallery

A technology of precast concrete and connection method, which is applied in construction, artificial island, infrastructure engineering, etc., can solve the problems of long construction period, leakage at the interface, and the interface is prone to upper and lower dislocation and deformation, and achieves the effect of controlling connection quality.

Active Publication Date: 2018-12-18
CHINA MCC17 GRP
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] With the continuous progress of society and the continuous development of science and technology, underground pipe galleries are widely used in modern cities. Cast-in-place concrete pipe galleries often cannot be constructed normally due to rainy days, and the construction period is very long. Precast concrete pipe galleries are constructed in pipe galleries. However, the disadvantage of prefabricated concrete pipe gallery is that its interface is prone to dislocation and deformation due to uneven foundation settlement, which causes leakage and fracture at the interface.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A connection method for prefabricated concrete pipe gallery
  • A connection method for prefabricated concrete pipe gallery
  • A connection method for prefabricated concrete pipe gallery

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0019] A method for connecting a prefabricated concrete pipe gallery, the method comprising the following steps:

[0020] Step A. Install the positioning plate 1. Before the prefabricated concrete pipe gallery, the positioning plate 1 is pre-embedded at the section of the concrete pipe gallery, and the positioning plate 1 is fixed by the positioning plate base 7; the fixing method of the positioning plate 1 and the positioning plate base 7 is as follows: snap-fit ​​connection, and the four inner corners of the positioning plate 1 are not provided with reinforcement plates 8;

[0021] Step B. Build the section frame of the prefabricated concrete pipe gallery, install the embedded steel pipes 2 in the positioning holes 101 on the surface of the positioning plate 1, and the distance between the embedded steel pipes 2 is determined according to the calculation of the stress situation; among them, the embedded steel pipes 2 The length is 200mm, and both ends of the pre-embedded ste...

Embodiment 2

[0025] A method for connecting a prefabricated concrete pipe gallery, the method comprising the following steps:

[0026] Step A. Install the positioning plate 1. Before the prefabricated concrete pipe gallery, the positioning plate 1 is pre-embedded at the section of the concrete pipe gallery, and the positioning plate 1 is fixed by the positioning plate base 7; the fixing method of the positioning plate 1 and the positioning plate base 7 is as follows: Welding connection, and the positioning plate 1 has reinforcement plates 8 at the four inner corners;

[0027] Step B. Build the section frame of the prefabricated concrete pipe gallery, install the embedded steel pipes 2 in the positioning holes 101 on the surface of the positioning plate 1, and the distance between the embedded steel pipes 2 is determined according to the calculation of the stress situation; among them, the embedded steel pipes 2 The length is 225 mm, and both ends of the pre-embedded steel pipe 2 are blocke...

Embodiment 3

[0031] A method for connecting a prefabricated concrete pipe gallery, the method comprising the following steps:

[0032] Step A. Install the positioning plate 1. Before the prefabricated concrete pipe gallery, the positioning plate 1 is pre-embedded at the section of the concrete pipe gallery, and the positioning plate 1 is fixed by the positioning plate base 7; the fixing method of the positioning plate 1 and the positioning plate base 7 is as follows: Bolt connection, and the positioning plate 1 has reinforcement plates 8 at the four inner corners;

[0033] Step B. Build the section frame of the prefabricated concrete pipe gallery, install the embedded steel pipes 2 in the positioning holes 101 on the surface of the positioning plate 1, and the distance between the embedded steel pipes 2 is determined according to the calculation of the stress situation; among them, the embedded steel pipes 2 The length is 250mm, and both ends of the pre-embedded steel pipe 2 are sealed wit...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a concrete pipe rack precasting connecting method. The connecting method comprises the following steps that before a concrete pipe rack is precasted, a positioning plate is pre-buried on the section of the concrete pipe rack, accurate positioning of pre-buried steel pipes is guaranteed, and the positioning plate is fixed with a positioning plate base; the pre-buried steel pipes are mounted through positioning holes on the positioning plate, spacing between the pre-buried steel pipes are determined according to calculating of stressing conditions, and the pre-buried steel pipes penetrate through the positioning plate through the positioning holes; and pipe rack precasting is conducted after the positioning plate and the pre-buried steel pipes are mounted, after pipe rack precasting is finished, the pipe rack is conveyed to a construction site to be mounted, during pouring, the part, near a foundation, of a connector of the pipe rack is firstly poured, and then the rest parts of the pipe rack are poured through a stereotyped steel mould. The concrete pipe rack precasting connecting method has the beneficial effects that the problems that due to the fact such as uneven settlement of the foundation, up and down dislocation and deformation of the connector of the precast concrete pipe rack are prone to occur, and the phenomena of connector leakage and breakage are caused are effectively solved, and the connecting quality of the connector of the precast concrete pipe rack is effectively controlled.

Description

technical field [0001] The invention discloses a connection method, in particular to a connection method for a prefabricated concrete pipe gallery, and belongs to the technical field of construction methods. Background technique [0002] With the continuous progress of society and the continuous development of science and technology, underground pipe galleries are widely used in modern cities. Cast-in-place concrete pipe galleries often cannot be constructed normally due to rainy days, and the construction period is very long. Precast concrete pipe galleries are constructed in pipe galleries. It has been gradually popularized and applied, but the disadvantage of precast concrete pipe gallery is that its interface is prone to dislocation and deformation due to uneven settlement of the foundation, which causes leakage and fracture at the interface. Therefore, in view of the above problems, a connection method of precast concrete pipe gallery is proposed. Contents of the inve...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045
CPCE02D29/10
Inventor 倪淑梅
Owner CHINA MCC17 GRP