A connection method for prefabricated concrete pipe gallery
A technology of precast concrete and connection method, which is applied in construction, artificial island, infrastructure engineering, etc., can solve the problems of long construction period, leakage at the interface, and the interface is prone to upper and lower dislocation and deformation, and achieves the effect of controlling connection quality.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0019] A method for connecting a prefabricated concrete pipe gallery, the method comprising the following steps:
[0020] Step A. Install the positioning plate 1. Before the prefabricated concrete pipe gallery, the positioning plate 1 is pre-embedded at the section of the concrete pipe gallery, and the positioning plate 1 is fixed by the positioning plate base 7; the fixing method of the positioning plate 1 and the positioning plate base 7 is as follows: snap-fit connection, and the four inner corners of the positioning plate 1 are not provided with reinforcement plates 8;
[0021] Step B. Build the section frame of the prefabricated concrete pipe gallery, install the embedded steel pipes 2 in the positioning holes 101 on the surface of the positioning plate 1, and the distance between the embedded steel pipes 2 is determined according to the calculation of the stress situation; among them, the embedded steel pipes 2 The length is 200mm, and both ends of the pre-embedded ste...
Embodiment 2
[0025] A method for connecting a prefabricated concrete pipe gallery, the method comprising the following steps:
[0026] Step A. Install the positioning plate 1. Before the prefabricated concrete pipe gallery, the positioning plate 1 is pre-embedded at the section of the concrete pipe gallery, and the positioning plate 1 is fixed by the positioning plate base 7; the fixing method of the positioning plate 1 and the positioning plate base 7 is as follows: Welding connection, and the positioning plate 1 has reinforcement plates 8 at the four inner corners;
[0027] Step B. Build the section frame of the prefabricated concrete pipe gallery, install the embedded steel pipes 2 in the positioning holes 101 on the surface of the positioning plate 1, and the distance between the embedded steel pipes 2 is determined according to the calculation of the stress situation; among them, the embedded steel pipes 2 The length is 225 mm, and both ends of the pre-embedded steel pipe 2 are blocke...
Embodiment 3
[0031] A method for connecting a prefabricated concrete pipe gallery, the method comprising the following steps:
[0032] Step A. Install the positioning plate 1. Before the prefabricated concrete pipe gallery, the positioning plate 1 is pre-embedded at the section of the concrete pipe gallery, and the positioning plate 1 is fixed by the positioning plate base 7; the fixing method of the positioning plate 1 and the positioning plate base 7 is as follows: Bolt connection, and the positioning plate 1 has reinforcement plates 8 at the four inner corners;
[0033] Step B. Build the section frame of the prefabricated concrete pipe gallery, install the embedded steel pipes 2 in the positioning holes 101 on the surface of the positioning plate 1, and the distance between the embedded steel pipes 2 is determined according to the calculation of the stress situation; among them, the embedded steel pipes 2 The length is 250mm, and both ends of the pre-embedded steel pipe 2 are sealed wit...