Blocking program of tail locks of diversion tunnel group
A technology of diversion tunnels and procedures, applied in water conservancy projects, hydroelectric power stations, hydroelectric power generation, etc., can solve the risk of increasing the structural risk of the inlet during the blocking period, the bias pressure of the intermediate pier, and the safety risk of the water retaining structure at the entrance of the diversion tunnel. major problems, to achieve the effect of improving the stress conditions of the import structure, improving the structural safety, and improving the safety of the import structure
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] The implementation of the present invention will be described in detail below in conjunction with the accompanying drawings, but they do not constitute a limitation to the present invention, they are only examples, and at the same time, the advantages of the present invention will become clearer and easier to understand.
[0029] refer to Figure 1-3 Shown: a diversion tunnel group lower gate plugging procedure, it includes the following steps:
[0030] ①. Firstly, the first batch of diversion tunnels 1 are opened, and the second batch of diversion tunnels 2 that have not been opened are used to discharge the upstream water during the construction period. The small-capacity hoist 4 lowers the gate and lowers the water head to block the gate 3 to block the water, creating the first batch of diversion tunnels in the first dry land construction conditions; (the arrow in the figure indicates the direction of water flow)
[0031] 2. Carry out temporary plugging 6 constructi...