A construction method for tunnel waterproof board without longitudinal construction joints
A construction method and technology of construction joints, which are applied in tunnels, tunnel linings, drainage, etc., can solve the problems of welding quality of construction joints, affecting waterproof and drainage effects, and inability to ensure smooth drainage of tunnels, etc., and achieve the effect of wide application range
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0016] A construction method for a tunnel waterproof board without longitudinal construction joints, comprising the following steps:
[0017] (1) Substrate treatment
[0018] Before construction, the empty ballast, sundries, mud, and accumulated water at the bottom of the tunnel should be cleaned up, and the bottom of the tunnel should be blown clean with high-pressure air. Bottom reprocessed.
[0019] (2) Install the vertical reserved groove formwork
[0020] After the inverted arch reinforcement and formwork are completed, the reserved groove formwork construction will be carried out. The template for the reserved groove is assembled in the hole of the shaped steel template, and it is reinforced firmly. The gap at the joint is pasted with double-sided adhesive tape. The distance to the tunnel centerline varies.
[0021] (3) Horizontal drainage pipe installation
[0022] The horizontal drainage pipe is a hydraulic channel connecting the vertical drainage pipe and the cen...