Construction method for underneath passing of road section with heavy traffic pressure
A construction method and pressure technology, applied in the direction of roads, roads, tunnels, etc., can solve problems affecting traffic, etc., and achieve the effects of shortening the construction period, reducing impact, and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0023] The embodiment of the present invention will be described in detail below in conjunction with the accompanying drawings. This embodiment is implemented on the premise of the technical solution of the present invention, and detailed implementation methods and specific operating procedures are provided, but the protection scope of the present invention is not limited to the following the embodiment.
[0024] The technical solution of the present invention is: a construction method for underpassing a road section under heavy traffic pressure, comprising the following steps:
[0025] S1. Set pile type ground anchor as pile foundation;
[0026] S2. Install prestressed concrete portals at both ends of the subgrade, and drill holes along the direction of the portals at equal distances on the subgrade to generate reserved grouting holes 11. Both the subgrade and the portals are set on pile-type ground anchors, and the portals The bottom is connected with the pile anchor;
[0...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com